This method statement outlines the procedures for Testing & Commissioning of Ventilation and Exhaust Fans in accordance with project specifications and approved shop drawings.
📌 2. Scope
Covers the complete process of Testing & Commissioning of all Ventilation and General Exhaust Fan Units per:
Project Requirements
Manufacturer Instructions
Approved Shop Drawings
📌 3. References
✅ Latest approved HVAC fans shop drawings
✅ Project Quality Plan (PQP)
✅ Project HSE Plan
✅ Material Approvals
📌 4. Definitions
Here are key abbreviations used:
PQP – Project Quality Plan
PSP – Project Safety Plan
QCP – Quality Control Procedure
WIR – Work Inspection Request
MIR – Material Inspection Request
ASHRAE – Air Conditioning Society
SMACNA, ARI, ASME, NFPA, UL, BMS, NEMA, AMCA, TEFC, BS – Industry codes and standards
📌 5. Responsibilities
👨💼 Project Manager
Ensure smooth execution per project plan
Oversee safety & quality compliance
👷♂️ Construction Manager
Control and supervise site activities
Coordinate with QA/QC and Site Engineers
🧑💻 Site Engineer
Implement method statements
Monitor progress and ensure coordination
Respond to consultant comments
🧑🔧 QA/QC Engineer
Monitor site execution as per specs
Raise WIRs/MIRs and ensure inspections
Assist during consultant inspections
👨🔧 Site Foreman
Execute tasks in coordination with Site Engineer
Daily work reporting
Ensure safety and quality compliance
👷 Safety Officer
Enforce HSE Plan
Ensure proper PPE and tools are used
Monitor site for potential hazards
📦 Store Keeper
Manage proper material storage
Acknowledge deliveries in coordination with QA/QC
📌 6. Equipments Required
🔧 Basic Electrical Tools
🌬️ Pitot Tube / Air Flow Meters
💨 Anemometer
🔌 Multimeter (FLA reading)
🔄 Tachometer (Fan RPM)
✍️ Marker
🧰 Toolbox
🪜 Step Ladder
📌 7. Procedure
✅ General HSE Requirements
Safety signs and PPE mandatory
Commissioning Kick-Off Meeting
✅ Pre-Commissioning Checklist
PTW system in place
Pre-safety inspection
Approval of latest installation drawings
Inspected and approved materials/equipment
LOTO system active
Inspection tools ready
Stable power supply
⚙️ Commissioning Steps
🔁 Functional Test
Ensure pre-commissioning completed
Obtain approved PTW
Verify control panel commissioning
Check line voltage
Test motor operation and direction
Observe for unusual noises or vibrations
Record motor current and voltage readings
Ensure BMS control devices function properly
🔍 Testing & Balancing
Conducted by third-party agency
Follow approved procedures and specs
🔄 Post-Test Reinstatement
Sign-off on check/test sheets
Remove test instruments
Confirm no faults in system
Lock the control panel
🛠️ Preservation and Flat Condition
Ensure stable, complete power supply
Restrict access to authorized personnel only
Confirm no overheating or loose connections
📌 8. System-Specific Commissioning
🧪 Chemical Rooms
Operated via control panel or emergency push button
Fan starts during chemical spills
🍳 Kitchen Fans
OFF: Both extract & make-up fans off
ON: Both fans operate from kitchen control panel
🌬️ General Fans
OFF: Supply and extract fans off
ON: Controlled via local switch at normal operation
🧯 Staircase & Lift Pressurization Fans
Controlled by Fire Alarm Control Panel (FACP)
BMS monitors fan run/trip status and alarms
🔌 Generator Room
Fan interlocked with generator panel
Fan starts when generator operates
🚽 Toilet Exhaust Fans
Operated via roof control panel
Motorized damper opens with fan
Failure triggers automatic fan and damper operation
This method statement outlines the complete process for the installation, testing, and commissioning of the Smoke Management System, ensuring full compliance with the approved shop drawings and project specifications.
📍 2. Scope
Covers the procedures and guidelines to be followed for Smoke Management System installation in accordance with project specifications and manufacturer guidelines.
📚 3. References
Project Quality Plan (PQP)
Project HSE Plan (PSP)
Approved Shop Drawings
Material Approval Requests
SMACNA, ARI, UL, NEMA, AMCA, BS standards
🔍 4. Definitions
MS – Method Statement
WIR – Work Inspection Request
MAR – Material Approval Request
FSCS – Firefighter Smoke Control Station
HOA – Hand Off Auto Module (Full list retained in original document)
👥 5. Roles & Responsibilities
📌 Project Manager
Oversee work as per schedule
Ensure safety & quality coordination
Ensure availability of tools and equipment
📌 Construction Manager
Supervise on-site work
Approve WIRs
Coordinate with site & QA/QC teams
📌 Site Engineer
Implement method statement
Coordinate with QA/QC & Safety
Monitor daily progress
📌 QA/QC Engineer
Ensure installation as per drawings/specs
Raise WIRs/MIRs timely
Coordinate inspections & ensure clearance
📌 Site Foreman
Manage daily activities
Maintain progress reports
Coordinate with Site Engineer
📌 Safety Officer
Enforce HSE Plan
Train staff on safety practices
Maintain clean & hazard-free environment
📌 Store Keeper
Manage material receipt & storage
Ensure material approval & protection
🧰 6. Tools & Materials
Marker
Screwdrivers
Pliers
Multimeter
Test Lamp
🛠️ 7. Procedure
🔧 Installation
Check panel location per approved drawings
Install FSCS and HOA modules
Ensure earthing and connection points
Connect LED/switch controllers using ribbon and communication cables
👀 Visual Inspection
Confirm all components are installed properly
Verify alignment with drawings and specs
Ensure all labels and LEDs are correct
🔍 Pre-Commissioning (Cold Testing)
Confirm back box, cable markers, labels
Replace faulty items
Document checks in pre-commissioning checklist
⚡ Power-Up
Check 24V DC power and data cables
Ensure proper polarity and terminations
Energize FSCS Panel
✅ Testing & Commissioning
Notify personnel before testing fans (AHU, SPF, LPF, etc.)
Definition: Quality refers to the minimum requirements set by the client or the degree of excellence that a product, system, or service must meet.
Purpose: Ensures that the outcome fulfills its intended function effectively and meets customer satisfaction.
🛠️ Quality Assurance (QA)
Definition: QA is the systematic process of setting standards, procedures, and parameters to ensure the quality of a project from the start.
Focus: It is process-based, emphasizing prevention of defects rather than correction.
Timing: Done before Quality Control (QC).
Approach: It is a proactive tool aimed at improving work processes.
Involvement: Requires teamwork and planning.
🔍 Key QA Activities:
Defining project standards and specifications.
Providing training and instructions to team members.
Monitoring work processes.
Conducting inspections during the work process, not after.
Ensuring compliance with regulations and industry standards.
🧰 Example of QA in Construction:
Setting wiring standards before installation:
Type and size of wires to be used.
Proper installation procedures.
Training electricians to follow these standards.
Goal: Prevent issues like incorrect wire sizes or poor connections before they happen.
🔧 Quality Control (QC)
Definition: QC is the process of identifying, checking, and correcting defects in the final product or output.
Focus: It is product-based, ensuring the finished product meets set standards.
Timing: Done after QA, during or after work completion.
Approach: It is a corrective tool used to detect and fix mistakes.
🔍 Key QC Activities:
Visual inspections of the finished work.
Testing using tools (e.g., multimeters) to verify performance.
Checking compliance with codes and safety regulations.
Creating checklists and test reports to verify outcomes.
🧰 Example of QC in Construction:
After wiring is installed, the QC team:
Inspects the installation for visible defects.
Tests circuits to ensure they function correctly.
Ensures grounding and protection are done according to code.
If issues are found, they are corrected before project handover.
🆚 Difference Between QA and QC at a Glance
Feature
Quality Assurance (QA)
Quality Control (QC)
Orientation
Process-based
Product-based
Timing
Before execution
After execution
Focus
Preventing defects
Detecting and fixing defects
Approach
Proactive
Reactive
Responsibility
Standard setting and process design
Inspection and testing
Role of a QC Inspector During Shutdown in Saudi Aramco Projects
During a project shutdown, the Quality Control (QC) Inspector plays a critical role in ensuring that all project documentation and inspections meet Saudi Aramco’s stringent quality standards. Below is a detailed breakdown of responsibilities and procedures:
✅ Role of QC Inspector During Shutdown
Handover of Documentation: The QC Inspector must hand over all completed project documents to the client (Saudi Aramco) during the shutdown phase.
Ensure Compliance: Confirm that all project activities and materials have been inspected, documented, and approved in accordance with Aramco’s standards.
📊 Levels of Inspection in Aramco Projects
There are five levels of inspection, each with a specific scope:
Level 0 – Document Review
Reviewing and revising all technical and quality documents.
Level 1 – Pre-Shipment Inspection
Inspection conducted before the material is dispatched from the supplier.
Level 2 – Random Inspection / Surveillance
Occasional or surprise checks during project activities.
Level 3 – Periodic Inspections
Includes daily, weekly, or monthly inspections on-site.
Level 4 – Resident Inspection
Full-time inspection by QC personnel stationed on-site.
📦 Material Receiving Inspection – Key Checks
✅ Ensure that material suppliers are Saudi Aramco-approved.
✅ Delivery Note must match the Purchase Order (PO).
✅ Verify the presence of a Certificate of Material Handling, duly stamped by the manufacturer.
✅ Ensure the material itself is stamped and identifiable.
✅ Check for the Material Test Report (MTR) and validate its accuracy.
📁 Material Receiving Inspection – Required Attachments
📄 Delivery Notes
📄 Purchase Order
📄 Request for Technical Approval (RTA)
📄 Material Test Certificate (MTC)
📄 SATIP (Saudi Aramco Typical Inspection Plan)
📄 SAIC (Saudi Aramco Inspection Checklist)
🗂️ Complete List of Material Receiving Documents
📌 Purchase Order (PO)
📌 Delivery Notes (DN)
📌 Material Test Certificate (MTC)
📌 Material Technical Approval (MTA)
📌 Inspection Release Certificate (IRC)
📌 Vendor Approval for Level 0
📌 Material Request (MR) or MTA for Level 1
📄 Schedule “Q” – Quality Contract Document
Definition: A contractual quality document between client and contractor, specifying all QA/QC requirements.
This method statement describes the process for the installation, testing, and commissioning of the fire fighting sprinkler system as outlined in the project specifications and approved shop drawings.
2.0 SCOPE
This method covers the supply, installation, testing, and commissioning of the sprinkler system, following project requirements, approved drawings, specifications, and manufacturer instructions.
3.0 REFERENCES
Approved Shop Drawings for Fire Fighting System
Project Specifications
Project Quality Plan (PQP)
Health, Safety and Environment Plan (HSE Plan)
Approved Material Submittals
Inspection and Test Plan (ITP)
4.0 DEFINITIONS
Acronym
Description
PQP
Project Quality Plan
PSP
Project Safety Plan
QCP
Quality Control Procedure
HSE
Health, Safety, and Environment
MS
Method Statement
ITP
Inspection Test Plan
QA/QC
Quality Assurance / Quality Control Engineer
WIR
Work Inspection Request
MIR
Material Inspection Request
UPVC
Ultra Polyvinyl Chloride
HDPE
High-Density Polyethylene
PEX
Cross-linked Polyethylene
G.I. Pipe
Galvanized Iron Pipe
5.0 RESPONSIBILITIES
5.1 Project Manager
Ensure work is completed as per project schedule.
Ensure all tools and equipment are in good condition.
Coordinate safety and quality measures.
5.2 Construction Manager
Supervise and control site works.
Coordinate with QA/QC, site team, and foremen.
Approve WIRs before submitting to the Consultant.
5.3 Site Engineer
Implement method statement as per project specs and drawings.
Monitor progress and coordinate with QA/QC and Safety Engineers.
Ensure revised information is communicated to the foremen.
5.4 QA/QC Engineer (MEP)
Monitor site work compliance with drawings and specs.
Raise MIRs/WIRs and perform quality tests.
Coordinate inspections with the Consultant.
5.5 Site Foreman
Execute daily work and manage resources.
Submit daily progress reports.
Report unforeseen incidents immediately.
5.6 Safety Officer
Enforce HSE plan and site safety regulations.
Provide training and inspections.
Ensure PPE use, barricades, and lighting.
5.7 Store Keeper
Manage safe and organized storage of materials.
Coordinate with QA/QC for material receiving.
6.0 EQUIPMENT
Tool Box
Measuring Tape
Spirit Level
Pipe Cutting & Threading Machine
Step Ladder, Scaffolds, and Platforms
Torque Wrench
Electric Drill, Welding & Grinding Machines
Solvent Cement
Water Level Marker
Pressure Gauge
Hammer
7.0 PROCEDURE
7.1 General Requirements
Use only approved materials and inspect upon delivery.
Installation by qualified personnel following specifications.
MIR must be approved before installation.
7.2 Material Delivery & Storage
7.2.1 Delivery
Transport in covered packaging to prevent damage.
Handle carefully; avoid dropping or dragging.
7.3.1 Storage
Store indoors, protected from weather.
Keep equipment in original packaging until needed.
7.4 Installation Sequence
7.4.1 Safety
Follow HSE regulations.
Provide toolbox talks before work.
Use proper PPE and ensure safe access.
7.4.2 Pre-Installation
Confirm all installations and tests are approved.
Ensure civil works clearance.
Use approved shop drawings only.
Check for service clashes.
7.4.3 Installation Procedure
7.4.3.1 General System Description
Install as per NFPA 13 and manufacturer guidelines.
Sprinklers activate automatically during fire due to heat.
7.4.3.2 Detailed Installation
7.4.3.2.1 Sprinkler Heads
Install as per approved drawings.
Hand-tighten, then use a wrench.
Install escutcheon plates correctly.
Ensure proper alignment and spacing.
7.4.3.2.2 Butterfly Valves
Install where accessible.
Ensure proper valve support.
Do not force valve closed; inspect for debris.
Integrate fire alarm connections.
7.4.3.2.3 Flow Switches
Mount on horizontal (preferably top) or vertical pipes.
Drill hole as per manufacturer specs.
Ensure vane moves freely inside the pipe.
Connect to the fire alarm panel.
7.4.4 Testing & Commissioning
7.4.4.1 Visual Inspection & Testing
Verify hydrostatic testing is completed.
Ensure proper pipe support and equipment installation.
7.4.4.1.1 Flushing
Flush all risers before connecting sprinklers.
Use clean water and repeat if necessary.
Drain flushed water safely.
Conduct hydrostatic test afterward.
7.4.4.2 Commissioning
Calibrate all instruments before use.
Ensure all installations and supports are approved.
Pressurize the system using fire pumps.
Check for leaks and proper pressure on all floors.
Keep the system under observation for 24 hours.
Simulate fault and fire alarms using drain valves.
Verify water throw of hose reels (minimum 6m range).
This method statement covers the nature, type of work & application of the Installation, Testing & Commissioning of Wet Chemical Fire Suppression System for Kitchen Hoods for the project as mentioned in the Approved Shop Drawings & project specifications.
2.0 SCOPE:
Supply, Installation, Testing & Commissioning of Wet Chemical Fire Suppression System for Kitchen Hoods so as to ensure that the job execution complies with project requirements as indicated in the Approved Shop Drawings of Fire Protection System and complies with project specifications enable to serve for its intended purpose to the satisfactory level of the client.
3.0 REFERENCES:
Latest Approved shop drawings for the required and applicable areas for Fire Protection System.
Specifications
NFPA Standard
UL 300 Standards
Project Quality Plan
4.0 DEFINITIONS:
Main Contractor :
MEP Contractor :
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Request
MAR : Material Approval Request
UPVC Class E : Ultra polyvinyl chloride Class E
UPVC : Ultra polyvinyl chloride
HDPE : High density polyethylene
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:
Project Manager
Construction manager
QA/QC Engineer
Site Engineer
HSE officer
SK
5.1 Project Manager
The work progress shall be carried out as per planned program and all the equipment’s required to execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.
Project Manager is the overall responsible for the project in terms of work execution, safety, planning & quality. The Project Manager will maintain the planning progress and coordination of works with the main contractor.
5.2 Construction Manager
Construction Manager is responsible to supervise and control the work on site.
Coordinating with QA/QC Engineers, Site Team & Foremen for all activities on site.
Control and sign all WIRs before issuing to Consultant approval.
5.3 Site Engineer
The method of statement to the system shall be implemented according to the Consultant project specifications and approved shop drawings.
Provision of all necessary information and distribution of responsibilities to his Construction team.
The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.
The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.
The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the Inspection for the finished works.
He will ensure the implementation of any request that might be raised by the Consultant.
Efficient daily progress shall be obtained for all the equipment and manpower.
He will engage in the work and check the same against the daily report received from the Foremen.
The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.
5.4 QA/QC Engineer (MEP):
The monitoring of executions of works at site and should be as per the approved shop drawings and project specifications & material approval.
Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
He will follow and carried out all the relevant tests as per project specifications.
Obtain the required clearance prior to Consultant’s inspections.
Should acquire any necessary civil works clearances and coordination.
One who will assist the Consultant Engineer/ Inspector during Inspections.
5.5 Site Foreman
The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.
Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
5.6 Safety Officer
The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.
The implementation of safety measures is adequate to maintain a safe working environment on the work activity.
Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.
The site is maintained in a clean and tidy manner.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items as required.
Ensure adequate lighting is provided in the working area wherever required.
Ensure high risk elevated areas are provided with barricade, tape, safety nets and with ladders.
Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
Ensure safe access to site work at all times.
5.7 Store Keeper (SK)
Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
One who will acknowledge the receiving of materials at site in coordination with QA/QC & concerned Engineer.
6.0 EQUIPMENTS:
Following tools shall be arranged before starting the job.
Tool Box
Measuring Tape
Hack Saw Blade
Spirit Level
Electric Drill Machine
Step Ladders
Excavator
Solvent Cement (if required)
Electric welding machine. (if required)
Crimping Tool
Wire Cutter
Screw Drivers
7.0 PROCEDURE:
7.1General Requirements
All the materials received at site shall be as per the approved technical material submittal for Wet Chemical Fire Suppression System for Kitchen Hoods to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc, should be reported to the supplier for rectification or replacement & to be removed from site immediately.
All construction/inspections/testing works shall be carried out in accordance with specifications & to be done by qualified Mechanical Engineers and shall be checked and approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
Contractor has to clarify the procedure for material delivery to the site through consultant Engineer at site.
7.2 Handling & Storage
7.2.1 Handling
During transportation ensure that the materials are in a box or at least covered with plastic. Do not drop the materials especially on hard surfaces. This is particularly important as the materials might be broken, damaged & cause injuries to personnel.
Where ever possible the loading and offloading of the equipment & its component shall be carried out by hand.
When required or necessary, forklift shall be used in unloading the materials.
7.2.2 Storage
7.2.2.1 Storage on site
Wet chemical supplied / delivered shall be stored in the original closed shipping container supplied by the manufacturer. These containers shall not be opened unless otherwise instructed by the Consultant.
Wet chemicals supplied/ delivered shall be maintained within the manufacturer’s recommended temperature range.
7.3 Sequence of Installation, Testing & Commissioning.
7.3.1 Safety
All site safety rules & regulations shall be complied with.
Supervisors will deliver tool box talks, relevant to this installation, to all operatives involved in the installation, and shall be recorded.
All operatives will be equipped with minimum personnel protective equipment; hard hat, safety boots, safety glasses.
The persons using cleaning fluid and solvent cement have to wear hand gloves.
All operatives shall fully understand the method of installing the abovementioned system.
7.3.2 Pre- Installation Procedure
Before commencement of installation activity, the supervisor must ensure that:
Permission to start or Civil Clearances prior to installation has been given by the main contractor.
Materials have been inspected & approved by the Engineer during the delivery via MIR.
All relevant Shop drawings for intended for the system in relevance to the area of use have been approved by the Consultant.
Necessary openings in the floor (if required) are provided as per the approved builders work drawing.
Scaffolding/ ladders if necessary & required for installations are correctly built, safe & suitable for the purpose.
Floor Finish level and finish data are available to coordinate with all the elevations & distances required in the installations.
7.3.3 Installation Procedure
Ensure the correct type and model of the material as per the approved material submittal.
If necessary or required, mock-up will be installed and approved by the Consultant prior to further installations.
Ensure that all pipe works/ duct works has been completed, tested & approved by the Consultant.
Mark the locations for the cylinders, manual pull stations & pipe routings as per approved shop drawings & support details.
Install the Wet Chemical Fire Suppression System at the right location as per Approved drawings.
For any discrepancies on the distances & elevations as per the approved drawings shall be marked “red line” on the drawings & shall be incorporated in the as-built drawings.
Fix supports & brackets in a vertical position as per support details in the approved working drawing or as recommended by the manufacturer. Ensure that all fixings are secure & durable to hold the cylinder.
Install the valve assemblies in an upright position. A shelf bracket is required for use with the cylinder & valve assembly.
Recheck the position, distance & elevations of installed brackets & supports.
Appropriate holes shall be drilled on the hood for pipe entry, nozzle dropping & plenum entry.
Piping supports shall be fixed to the surface of the hood using the approved material for threaded rods, nuts, washers & clamps.
Pipes shall be cut & threaded as per the dimensions required.
Fusible links along with the housing kit shall be installed & used for each applications as well as one in every exhaust duct.
Stainless steel rope shall be connected inside the pipe between the fusible links & cylinders & also from the manual pull station to cylinder.
Cable shall be pulled from the cylinder control head to the Fire Alarm Panel.
Appropriate terminations shall be done on the cylinder control head (Normally Open/ Normally Close Terminals) as well as on the Fire Alarm Panel.
7.3.4 Testing & Commissioning
Upon completion of Installation, the system shall be tested in accordance to the specification & manufacturer’s recommendation & all tests shall be approved by the Consultant thru the Testing & Commissioning Procedures as follows:
Check the installation of the cylinder as per the approved locations, elevations & distances stated in the approved shop drawings.
Check all supports if properly & correctly installed as per the approved Support Details or Manufacturer’s Recommendations.
Check installation of Control Head & Control Valve Assembly.
Check installation of Remote Release Pull Station.
Check the fusible links if properly fitted with the required clearance.
Check the pipes are supported & nozzles are positioned properly.
Check the actuation hose is connected between control head and valve.
Ensure that the control valve is removed from the cylinder.
Install the test cartridge inside the control head.
Cut the “S” hook from the last fusible link.
Ensure that the control valve is operated.
Remove the empty test cartridge and reset the control valve.
Replace the “S” hook and reset the control head.
Remove the safety pin & operate the remote release pull station.
Ensure Control mechanism is operated.
Reset the control head.
Install one cartridge inside the control head & fix the control valve on the cylinder.
This method statement is applicable for the Installation of Water Booster Pumps for the project as mentioned in the Specifications & Approved Shop Drawings.
2.0 SCOPE:
This method Statement shall cover the Supply & Installation of Water Booster Pumps in line with project requirements as indicated in the Approved Shop Drawings & specifications.
3.0 REFERENCES:
Latest Approved shop drawings intended for the Water Booster Pumps
Specifications
Project Quality Plan
Project HSE Plan
Material Approval
4.0 DEFINITIONS:
PQP : Project Quality Plan
PSP : Project Safety Plan
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection Request
MIR : Material Inspection Request
UPVC Class E : Ultra polyvinyl chloride
UPVC : Ultra polyvinyl chloride
HDPE : High density polyethylene
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:
Project Manager
Construction manager
QA/QC Engineer
Site Engineer
HSE officer
SK
5.1 Project Manager
The work progress shall be carried out as per planned program and all the equipment’s required to execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.
5.2 Construction Manager
Construction Manager is responsible to supervise and control the work on site.
Coordinating with QA/QC Engineers, Site Team & Foremen for all activities on site.
Control and sign all WIRs before issuing to Consultant approval.
5.3 Site Engineer
The method of statement to the system shall be implemented according to the Consultant project specifications and approved shop drawings.
Provision of all necessary information and distribution of responsibilities to his Construction team.
The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.
The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.
The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the Inspection for the finished works.
He will ensure the implementation of any request that might be raised by the Consultant.
Efficient daily progress shall be obtained for all the equipment and manpower.
He will engage in the work and check the same against the daily report received from the Foremen.
The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.
5.4 QA/QC Engineer (MEP):
The monitoring of executions of works at site and should be as per the approved shop drawings and project specifications.
Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
He will follow and carries out all the relevant tests as per project specifications.
Obtain the required clearance prior to Consultant’s inspections.
Should acquire any necessary civil works clearances and coordination.
QA/QC Engineer will assist the Consultant Engineer/ Inspector during Inspection.
Site Foreman
The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.
Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
5.6 Safety Officer
The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.
The implementation of safety measures is adequate to maintain a safe working environment on the work activity.
Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.
The site is maintained in a clean and tidy manner.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items as required.
Ensure adequate lighting is provided in the working area at night time.
Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.
Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
Ensure safe access to site work at all times.
5.7 Store Keeper (SK)
Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
One who will acknowledge the receiving of materials at site in coordination with QA/QC & concerned Engineer.
6.0 EQUIPMENTS:
Following tools shall be arranged before starting the job.
Tool Box.
Measuring Tape.
Hack Saw Blade
Spirit Level
Electric Drill Machine
Step Ladders
Threading Machine
Solvent Cement
Electric welding machine. (if required)
Torque Wrench
Ammeter
Digital Multimeter
Pressure Gauge
7.0 PROCEDURE:
Work Sequence/Procedure
7.1General Requirements
All the materials received at site shall be as per the approved technical material submittal and Water Booster Pump set to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc, should be reported to the supplier for rectification or replacement & to be removed from site immediately.
All construction/inspection/testing works shall be carried out in accordance with the specifications & to be done by qualified Mechanical Engineers and shall be checked and approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
Contractor has to clarify the procedure for material delivery to the site through consultant Engineer at site.
7.2 Handling
7.2.1 Material Transport/ Delivery
During transportation ensure that the equipment & its components (if any) are delivered in a shipping package and or shall be at least in a box covered with plastic. Extra care in unloading the equipment is required to avoid scratching or denting of finished surfaces of the Pumps & Frames.
Where ever possible the loading and offloading of the Water Booster Pumps shall be carried out by hand.
When required or necessary, forklift shall be used in unloading the materials.
Equipment shall not be dropped onto hard surfaces & should not be dragged along the ground.
7.3 Storage
7.3.1 Storage on Site Store
To ensure that deterioration of Water Booster Pumps does not occur during storage, it is recommended to store the pumps & its components in sheltered conditions that are protected from weather elements and accidental damage.
Water Booster Pumps & its components shall be protected with plastic or cardboard and the area shall be barricaded with warning signs.
7.4 Sequence of Installation for Water Booster Pumps:
7.4.1 Safety
All site safety rules & regulations shall be complied with.
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the installation, testing & commissioning and shall be recorded.
All operatives will be equipped with minimum personnel protective equipment; hard hat, coveralls, safety boots, safety glasses.
The persons using cleaning fluid and solvent cement have to wear hand gloves.
Ensure that all operatives fully understand the method of these activities.
7.4.2 Pre- Installation Procedure
Before commencement of installation activity, the supervisor must ensure that:
Delivered Booster Pumps Set have been inspected & approved via MIR by the consultant prior to installation at site.
Relevant documents or certificates shall be presented at the time of inspection if required by the Consultant.
Permission to start or Civil Clearances prior to installation has been given by the main contractor.
All relevant Shop drawings for the installation of Water Booster Pumps shall be available & approved by the consultant. No installation shall be done without Approved Shop Drawings.
Installation activities shall only commence when all associated works by the Civil such as clearing of work place, construction of concrete plinth, water proofing, painting of walls/ floor etc. have been verified & completed.
Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in charge at site.
Inspect the relevant area for any possible clashes with other services.
Pumps shall be moved to the work area in a safe manner and shall not block access/ egress from the site with the help of a 3 ton pick- up and or a fork lift.
7.4.3 Installation Procedure
Prior to installation, ensure that the data on the name plate matches with the required system data i.e. operating voltage, frequency & pump liquid temperature etc. MIR of the Water Booster Pumps should be approved by the Consultant.
Prior to placing the Water Booster Pumps Set in concrete plinth, make sure that the anchoring bolts are matching with the Pump steel base anchoring hole alignment.
Lay-out, marked & drill the location of the anchoring bolts on the concrete plinth.
Each pump shall be mounted on a neoprene rubber pad concrete.
Carefully place the Water Booster Pumps Set into the plinth. Check proper alignment and level by the use of a Torque Wrench.
Place the nuts with one flat and lock washer, tight the nuts up to the required torque.
After completion of setting-out of the Water Booster Pumps, lay-out and fabricate the suction & discharge piping and supports.
Install the fabricated pipes and fittings along with the valves, flexible connectors & strainers as per the approved shop drawings.
After completion of installation, raise an inspection request thru WIR to the Consultant for acceptance or Approval. Keep record for reference.
Once installation has been accepted & approved by the Consultant, provide covering material to the Installed Water Booster Pump to avoid entry of dirt and dust. Remove all covers when termination of cables will start.
Testing & Commissioning shall commence after final approval of the installation by the consultant.
The purpose of generating this method statement is to define the procedure step by step to implement the correct practices for Installation of Sump Pump through the guidelines contained herein so as to ensure that the job execution complies with the requirements of contract specification and serves the intended function to satisfactory level.in all applicable areas for the project.
2.0 SCOPE:
This method statement covers all processes related to Installation of Sump pump.
This procedure is to be read in conjunction with the relevant ITP, outlining the responsibility and the quality verification to be performed by various parties.
3.0 REFERENCES:
Latest Approved shop drawings for the required and applicable areas for plumbing system.
Specifications
Project Quality Plan
Material Submittals
4.0 DEFINITIONS:
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Inspection Report
5.0 RESPONSIBILITIES:
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:
Project Manager
Construction manager
QA/QC Engineer
Site Engineer
HSE officer
SK
5.1 Project Manager
The work progress shall be carried out as per planned program and all the equipment’s required to execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.
5.2 Construction Manager
Construction Manager is responsible to supervise and control the work on site.
5.3 Site Engineer
The method of statement to the system shall be implemented according to the Consultant project specifications and approved shop drawings.
Provision of all necessary information and distribution of responsibilities to his Construction team.
The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.
The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.
The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the Inspection for the finished works.
He will ensure the implementation of any request that might be raised by the Consultant.
Efficient daily progress shall be obtained for all the equipment and manpower.
He will engage in the work and check the same against the daily report received from the Foremen.
The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.
5.4 QA/QC Engineer (MEP):
The monitoring of executions of works at site and should be as per the approved shop drawings and project specifications.
Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
He will follow and carried out all the relevant tests as per project specifications.
Obtain the required clearance prior to Consultant’s inspections.
Should acquire any necessary civil works clearances and coordination.
5.5 Site Foreman
The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.
Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.
5.6 Safety Officer
The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.
The implementation of safety measures is adequate to maintain a safe working environment on the work activity.
Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.
The site is maintained in a clean and tidy manner.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items as required.
Ensure adequate lighting is provided in the working area at night time.
Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders also to Ensure of provided warning tapes in manhole places.
Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
Ensure safe access to site work at all times.
5.7 Store Keeper (SK)
Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
6.0 EQUIPMENT:
Tool box
Measuring tape
Marker
Wood-saw
Half round file
Wooden half round file
Hack-saw frame
Drill machine
Concrete bit
Moveable Hook/ Pulley
Anchor punch
Marking line-dori
Screw driver (flat & set)
Fix spanner (4mm to 32 mm)
Adjustable spanner
Sprite level
Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest, and safety gloves to ensure maximum ability of safe work and dust mask when required.
7.0 PROCEDURE:
7.1 Safety
Ensure only trained persons shall operate the power tools.
Ensure all concerned personnel shall use PPE (Personal Protective Equipment) and all other items as required.
Ensure adequate lighting is provided in the working area at night time.
Ensure service area/work area openings are provided with barricade, tape, and safety nets.
7.2 Work Sequence And Methodology
Check all material delivered to site is inspected properly by QA/QC Engineer and check if it is stored properly as per manufacturer’s recommendations.
MIR shall be raised for the inspection of the delivered sump pumps on site Consultant approval.
Work shall be carried out by the site staff under strict supervision and guidance of the concerned Supervisors / Foremen / Engineers.
The QA/QC Engineer shall check the Installations as per Check list items.
WIR shall be prepared by QA/QC Engineer and will be submitted to Consultant for their inspection and approval.
QA/QC Engineer shall coordinate with other Contractors and arrange inspection for installation to the Consultant Engineer.
QA/QC Engineer is responsible for all installation activities for getting the work inspected / approved by Consultant Engineer.
7.3 Handling and Storage
On receipt of sump pumps at site, necessary precautions shall be taken for unloading, shifting, and storage as follows:
Any Sump pumps & accessories deliver at site shall be carefully off-loaded by deploying necessary manpower in such a way that no damage shall caused to it.
All pumps & accessories shall be inspected, handled and stored properly upon receipt at site and after consultant approval for the material.
Pumps and accessories shall be stored in a place free of water, dust and adequately covered to avoid any kind of damages.
Pump shall be transported to work place using adequate manpower.
Any discrepancies, damage, and etc. found to the materials will be notified and reported to QA/QC Engineer and Project Engineer for further action.
Materials found not suitable for site use should be removed from site immediately.
All materials to be used shall be as per consultant MAR procedure and approval.
7.4 Installation of the sump pump
Obtain clearance from the civil work prior installation of sump pump.
Make sure that Sump pump material inspection is done.
Sump pit depth should be checked and as per approved shop drawings & builder work drawings.
Mark the pump location matching with proper guide rail location as per approved shop drawings and builder work drawings.
Install the pump as per specification and approved shop drawings.
Confirming to the matching line of flange install the guide rail and supporting chain.
Ensure all support as per manufacturer recommendation and approved shop drawings.
All Piping to be done in accordance to approved drawings and pump out let size.
Gate valve and PRV to be install properly.
All valves and major fittings to be supported properly.
Install relevant float switches.
Install the Control panel for the sump pump as per approved shop drawings and manufacturer recommendation.
As per manufacturer’s recommendation, pumps shall be lifted with the cabtyre cable lifted slightly. Secure it to the hook. A hook must be prepared in advance by placing it on the frame of a manhole. Refer to attached Manufacturer’s recommendation.
Raise inspection for Consultant approval after completion of the work.
7.5 Connections
Connection of the piping will be as per approved shop drawings and manufacturer recommendation indicate general arrangement of piping, fittings, and specialties.
Install piping adjacent to equipment to allow service and maintenance.