Method Statement for Testing & Commissioning of Ventilation and Exhaust Fans

📌 1. Purpose

This method statement outlines the procedures for Testing & Commissioning of Ventilation and Exhaust Fans in accordance with project specifications and approved shop drawings.


📌 2. Scope

Covers the complete process of Testing & Commissioning of all Ventilation and General Exhaust Fan Units per:

  • Project Requirements
  • Manufacturer Instructions
  • Approved Shop Drawings

📌 3. References

  • ✅ Latest approved HVAC fans shop drawings
  • ✅ Project Quality Plan (PQP)
  • ✅ Project HSE Plan
  • ✅ Material Approvals

📌 4. Definitions

Here are key abbreviations used:

  • PQP – Project Quality Plan
  • PSP – Project Safety Plan
  • QCP – Quality Control Procedure
  • WIR – Work Inspection Request
  • MIR – Material Inspection Request
  • ASHRAE – Air Conditioning Society
  • SMACNA, ARI, ASME, NFPA, UL, BMS, NEMA, AMCA, TEFC, BS – Industry codes and standards

📌 5. Responsibilities

👨‍💼 Project Manager

  • Ensure smooth execution per project plan
  • Oversee safety & quality compliance

👷‍♂️ Construction Manager

  • Control and supervise site activities
  • Coordinate with QA/QC and Site Engineers

🧑‍💻 Site Engineer

  • Implement method statements
  • Monitor progress and ensure coordination
  • Respond to consultant comments

🧑‍🔧 QA/QC Engineer

  • Monitor site execution as per specs
  • Raise WIRs/MIRs and ensure inspections
  • Assist during consultant inspections

👨‍🔧 Site Foreman

  • Execute tasks in coordination with Site Engineer
  • Daily work reporting
  • Ensure safety and quality compliance

👷 Safety Officer

  • Enforce HSE Plan
  • Ensure proper PPE and tools are used
  • Monitor site for potential hazards

📦 Store Keeper

  • Manage proper material storage
  • Acknowledge deliveries in coordination with QA/QC

📌 6. Equipments Required

  • 🔧 Basic Electrical Tools
  • 🌬️ Pitot Tube / Air Flow Meters
  • 💨 Anemometer
  • 🔌 Multimeter (FLA reading)
  • 🔄 Tachometer (Fan RPM)
  • ✍️ Marker
  • 🧰 Toolbox
  • 🪜 Step Ladder

📌 7. Procedure

✅ General HSE Requirements

  • Safety signs and PPE mandatory
  • Commissioning Kick-Off Meeting

✅ Pre-Commissioning Checklist

  • PTW system in place
  • Pre-safety inspection
  • Approval of latest installation drawings
  • Inspected and approved materials/equipment
  • LOTO system active
  • Inspection tools ready
  • Stable power supply

⚙️ Commissioning Steps

🔁 Functional Test

  • Ensure pre-commissioning completed
  • Obtain approved PTW
  • Verify control panel commissioning
  • Check line voltage
  • Test motor operation and direction
  • Observe for unusual noises or vibrations
  • Record motor current and voltage readings
  • Ensure BMS control devices function properly

🔍 Testing & Balancing

  • Conducted by third-party agency
  • Follow approved procedures and specs

🔄 Post-Test Reinstatement

  • Sign-off on check/test sheets
  • Remove test instruments
  • Confirm no faults in system
  • Lock the control panel

🛠️ Preservation and Flat Condition

  • Ensure stable, complete power supply
  • Restrict access to authorized personnel only
  • Confirm no overheating or loose connections

📌 8. System-Specific Commissioning

🧪 Chemical Rooms

  • Operated via control panel or emergency push button
  • Fan starts during chemical spills

🍳 Kitchen Fans

  • OFF: Both extract & make-up fans off
  • ON: Both fans operate from kitchen control panel

🌬️ General Fans

  • OFF: Supply and extract fans off
  • ON: Controlled via local switch at normal operation

🧯 Staircase & Lift Pressurization Fans

  • Controlled by Fire Alarm Control Panel (FACP)
  • BMS monitors fan run/trip status and alarms

🔌 Generator Room

  • Fan interlocked with generator panel
  • Fan starts when generator operates

🚽 Toilet Exhaust Fans

  • Operated via roof control panel
  • Motorized damper opens with fan
  • Failure triggers automatic fan and damper operation

📌 9. Attachments

  • 📄 Inspection & Test Plan
  • 📋 Pre-Commissioning Check Sheet
  • ✅ Testing & Commissioning Check Sheet
  • 🏷️ Commissioning Certificate Form
  • 📝 Handover Certificate Form
  • ❌ Punch List Form
  • ⚠️ Risk Assessment
  • 📊 Fans Schedule
  • 🗺️ Drawing Attachments
smoke management system

Method Statement for Smoke Management System: Installation, Testing & Commissioning Guide

📌 Table of Contents

  1. Purpose
  2. Scope
  3. References
  4. Definitions
  5. Roles & Responsibilities
  6. Tools & Materials
  7. Step-by-Step Procedure
  8. Attachments

🎯 1. Purpose

This method statement outlines the complete process for the installation, testing, and commissioning of the Smoke Management System, ensuring full compliance with the approved shop drawings and project specifications.


📍 2. Scope

Covers the procedures and guidelines to be followed for Smoke Management System installation in accordance with project specifications and manufacturer guidelines.


📚 3. References

  • Project Quality Plan (PQP)
  • Project HSE Plan (PSP)
  • Approved Shop Drawings
  • Material Approval Requests
  • SMACNA, ARI, UL, NEMA, AMCA, BS standards

🔍 4. Definitions

  • MS – Method Statement
  • WIR – Work Inspection Request
  • MAR – Material Approval Request
  • FSCS – Firefighter Smoke Control Station
  • HOA – Hand Off Auto Module
    (Full list retained in original document)

👥 5. Roles & Responsibilities

📌 Project Manager

  • Oversee work as per schedule
  • Ensure safety & quality coordination
  • Ensure availability of tools and equipment

📌 Construction Manager

  • Supervise on-site work
  • Approve WIRs
  • Coordinate with site & QA/QC teams

📌 Site Engineer

  • Implement method statement
  • Coordinate with QA/QC & Safety
  • Monitor daily progress

📌 QA/QC Engineer

  • Ensure installation as per drawings/specs
  • Raise WIRs/MIRs timely
  • Coordinate inspections & ensure clearance

📌 Site Foreman

  • Manage daily activities
  • Maintain progress reports
  • Coordinate with Site Engineer

📌 Safety Officer

  • Enforce HSE Plan
  • Train staff on safety practices
  • Maintain clean & hazard-free environment

📌 Store Keeper

  • Manage material receipt & storage
  • Ensure material approval & protection

🧰 6. Tools & Materials

  • Marker
  • Screwdrivers
  • Pliers
  • Multimeter
  • Test Lamp

🛠️ 7. Procedure

🔧 Installation

  • Check panel location per approved drawings
  • Install FSCS and HOA modules
  • Ensure earthing and connection points
  • Connect LED/switch controllers using ribbon and communication cables

👀 Visual Inspection

  • Confirm all components are installed properly
  • Verify alignment with drawings and specs
  • Ensure all labels and LEDs are correct

🔍 Pre-Commissioning (Cold Testing)

  • Confirm back box, cable markers, labels
  • Replace faulty items
  • Document checks in pre-commissioning checklist

⚡ Power-Up

  • Check 24V DC power and data cables
  • Ensure proper polarity and terminations
  • Energize FSCS Panel

✅ Testing & Commissioning

  • Notify personnel before testing fans (AHU, SPF, LPF, etc.)
  • Test damper OPEN/CLOSE buttons and LEDs
  • Test ON/OFF/AUTO switches and LED indicators
  • Test LAMP switch for LED functionality

👨‍🔧 Witness Demonstration

  • Record results in T&C checklists
  • Final documentation and consultant sign-off

📎 8. Attachments

  • 📝 Inspection & Test Plan (ITP-6012-0200 Rev.03)
  • ✅ Check Sheet (FM-6012-0200 Rev.03)
  • ⚠️ Risk Assessment (RA-6012-0200 Rev.03)
QAQC, Schedule Q, SATIP, SAIC & NCR Guide for Saudi Aramco Projects

Complete Guide to QA/QC, Schedule Q, SATIP, SAIC & NCR in Saudi Aramco Projects:

What is Quality?

  • Definition: Quality refers to the minimum requirements set by the client or the degree of excellence that a product, system, or service must meet.
  • Purpose: Ensures that the outcome fulfills its intended function effectively and meets customer satisfaction.

🛠️ Quality Assurance (QA)

  • Definition: QA is the systematic process of setting standards, procedures, and parameters to ensure the quality of a project from the start.
  • Focus: It is process-based, emphasizing prevention of defects rather than correction.
  • Timing: Done before Quality Control (QC).
  • Approach: It is a proactive tool aimed at improving work processes.
  • Involvement: Requires teamwork and planning.

🔍 Key QA Activities:

  • Defining project standards and specifications.
  • Providing training and instructions to team members.
  • Monitoring work processes.
  • Conducting inspections during the work process, not after.
  • Ensuring compliance with regulations and industry standards.

🧰 Example of QA in Construction:

  • Setting wiring standards before installation:
    • Type and size of wires to be used.
    • Proper installation procedures.
    • Training electricians to follow these standards.
  • Goal: Prevent issues like incorrect wire sizes or poor connections before they happen.

🔧 Quality Control (QC)

  • Definition: QC is the process of identifying, checking, and correcting defects in the final product or output.
  • Focus: It is product-based, ensuring the finished product meets set standards.
  • Timing: Done after QA, during or after work completion.
  • Approach: It is a corrective tool used to detect and fix mistakes.

🔍 Key QC Activities:

  • Visual inspections of the finished work.
  • Testing using tools (e.g., multimeters) to verify performance.
  • Checking compliance with codes and safety regulations.
  • Creating checklists and test reports to verify outcomes.

🧰 Example of QC in Construction:

  • After wiring is installed, the QC team:
    • Inspects the installation for visible defects.
    • Tests circuits to ensure they function correctly.
    • Ensures grounding and protection are done according to code.
  • If issues are found, they are corrected before project handover.

🆚 Difference Between QA and QC at a Glance

FeatureQuality Assurance (QA)Quality Control (QC)
OrientationProcess-basedProduct-based
TimingBefore executionAfter execution
FocusPreventing defectsDetecting and fixing defects
ApproachProactiveReactive
ResponsibilityStandard setting and process designInspection and testing

Role of a QC Inspector During Shutdown in Saudi Aramco Projects

During a project shutdown, the Quality Control (QC) Inspector plays a critical role in ensuring that all project documentation and inspections meet Saudi Aramco’s stringent quality standards. Below is a detailed breakdown of responsibilities and procedures:


Role of QC Inspector During Shutdown

  • Handover of Documentation:
    The QC Inspector must hand over all completed project documents to the client (Saudi Aramco) during the shutdown phase.
  • Ensure Compliance:
    Confirm that all project activities and materials have been inspected, documented, and approved in accordance with Aramco’s standards.

📊 Levels of Inspection in Aramco Projects

There are five levels of inspection, each with a specific scope:

  • Level 0 – Document Review
    • Reviewing and revising all technical and quality documents.
  • Level 1 – Pre-Shipment Inspection
    • Inspection conducted before the material is dispatched from the supplier.
  • Level 2 – Random Inspection / Surveillance
    • Occasional or surprise checks during project activities.
  • Level 3 – Periodic Inspections
    • Includes daily, weekly, or monthly inspections on-site.
  • Level 4 – Resident Inspection
    • Full-time inspection by QC personnel stationed on-site.

📦 Material Receiving Inspection – Key Checks

  • ✅ Ensure that material suppliers are Saudi Aramco-approved.
  • Delivery Note must match the Purchase Order (PO).
  • ✅ Verify the presence of a Certificate of Material Handling, duly stamped by the manufacturer.
  • ✅ Ensure the material itself is stamped and identifiable.
  • ✅ Check for the Material Test Report (MTR) and validate its accuracy.

📁 Material Receiving Inspection – Required Attachments

  • 📄 Delivery Notes
  • 📄 Purchase Order
  • 📄 Request for Technical Approval (RTA)
  • 📄 Material Test Certificate (MTC)
  • 📄 SATIP (Saudi Aramco Typical Inspection Plan)
  • 📄 SAIC (Saudi Aramco Inspection Checklist)

🗂️ Complete List of Material Receiving Documents

  • 📌 Purchase Order (PO)
  • 📌 Delivery Notes (DN)
  • 📌 Material Test Certificate (MTC)
  • 📌 Material Technical Approval (MTA)
  • 📌 Inspection Release Certificate (IRC)
  • 📌 Vendor Approval for Level 0
  • 📌 Material Request (MR) or MTA for Level 1

📄 Schedule “Q” – Quality Contract Document

  • Definition: A contractual quality document between client and contractor, specifying all QA/QC requirements.

✍️ Contents of Schedule Q

  • General Documents
  • Quality Management System Requirements (QMSR)
  • Documentation Requirements (DR)
  • Management Responsibility (MR)
  • Resource Management (RM)
  • Project Realization / Erection (PR/EM)
  • Measurement, Analysis & Improvement (MA/I)

📎 Attachments of Schedule Q

  • Attachment 1: Contractor & Subcontractor Personnel Quality Qualification Requirements
  • Attachment 2: Saudi Aramco Standards & Procedures Containing Quality Requirements
  • Attachment 3: QA & QC Requirements for the Construction Phase
  • Attachment 4: QA & QC Requirements for Contractor-Supplied Material
  • Attachment 5: Summary of Quality System Deliverables
  • Attachment 6: Project-Specific Quality Requirements

📂 Documentation Chart

  • You are the GE Supervisor → Reporting to De Manager & his Manager.
  • You submit QC documents to the Project Manager.
  • Teams under your supervision:
    • Construction Department (under your field of QC)
  • Procurement Department:
    • Responsible for acquiring materials, goods, and services.

🏗️ Site Preparation – Know the Scope

  • Understand:
    • What is the project?
    • The project’s purpose
    • Project content
    • Civil scope of work

📐 IFC Drawings vs. Shop Drawings

  • IFC (Issued for Construction):
    • Defines “what to do”
    • Must be stamped and collected from QC/Document Control
  • Shop Drawings:
    • Shows “how to do it”

📆 Cut-off Date

  • Defines:
    • Project announcement year
    • Applicable standard of that year

📋 Important QA/QC Documents

  • SATIP: Saudi Aramco Typical Inspection Plan
  • SAIC: Saudi Aramco Inspection Checklist
  • SATTP: Sequence of QC inspection activities in 4 phases:
    1. Document Review
    2. Material Receiving
    3. Installation
    4. Pre-commissioning / Handover

🔍 SATIP Inspection Points

  • Hold Point: Activity cannot proceed without PID approval
  • Witness Point: PID is informed, but if absent, QC may proceed
  • Surveillance Point: For record only (RFI is raised)

SAIC – Inspection Checklist Includes

  • Surveillance
  • Witness
  • Hold
  • Review / Review & Hold
  • Result Types: Pass / Fail / N.A.
  • Refers to: SAES, SAMSS

🧾 RFI (Request for Inspection)

  • Raised by QC Inspector → To inform PID for inspection
  • Must be submitted 24–48 hours before inspection with specific time/date
  • RFI Includes:
    • Description, Time, Activity
    • SATIP, SAIC, IFC Drawings

NCR (Non-Conformance Report)

  • Issued via SAPQM System by Aramco
  • Definition: A report that identifies mismatch between actual condition and standards

🔍 4 Parts of an NCR

  1. Description: Location, issue, data
  2. Root Cause: Reason for deviation (e.g., damaged material scanner)
  3. Corrective Action: Action to fix the violation
  4. Preventive Action: Steps to prevent future occurrences
  • ACD (Agreed Completion Date): Time given to construction team to resolve NCR

⚠️ Types of Violations

  1. Minor Violation
    • Small standard breaches (e.g., concrete dropped from 1.5m instead of 1m)
  2. Moderate Violation
    • Repeated minor violation within 6 months
    • Violation of Schedule Q
    • QC absence from site
    • Violation affecting another activity (e.g., coating on uncured concrete)
  3. Major Violation
    • Company Integrity Violation (e.g., wrong materials installed)
    • Forgery (Fake Documentation)
    • Can result in injury, damage, or project failure
  • Escalation: A minor violation that becomes moderate due to repeated failure or missed ACD

👥 PIM – Pre-Inspection Meeting

  • Held before starting major construction activity

📘 Key Saudi Aramco Standards

  • SAEP-1150: Records of QC inspections, RFIs, NCRs
  • SAEP-381: Types and escalation of violations
  • MSAERB: Mandatory Saudi Aramco Engineering Requirements

kva to Amps Calculator

kVA to Amps Calculator

kVA to Amps Calculator

Method Statement for installation,Testing & commissioning of Sprinkler System.

1.0 PURPOSE

This method statement describes the process for the installation, testing, and commissioning of the fire fighting sprinkler system as outlined in the project specifications and approved shop drawings.


2.0 SCOPE

This method covers the supply, installation, testing, and commissioning of the sprinkler system, following project requirements, approved drawings, specifications, and manufacturer instructions.


3.0 REFERENCES

  • Approved Shop Drawings for Fire Fighting System
  • Project Specifications
  • Project Quality Plan (PQP)
  • Health, Safety and Environment Plan (HSE Plan)
  • Approved Material Submittals
  • Inspection and Test Plan (ITP)

4.0 DEFINITIONS

Acronym Description
PQP Project Quality Plan
PSP Project Safety Plan
QCP Quality Control Procedure
HSE Health, Safety, and Environment
MS Method Statement
ITP Inspection Test Plan
QA/QC Quality Assurance / Quality Control Engineer
WIR Work Inspection Request
MIR Material Inspection Request
UPVC Ultra Polyvinyl Chloride
HDPE High-Density Polyethylene
PEX Cross-linked Polyethylene
G.I. Pipe Galvanized Iron Pipe

5.0 RESPONSIBILITIES

5.1 Project Manager

  • Ensure work is completed as per project schedule.
  • Ensure all tools and equipment are in good condition.
  • Coordinate safety and quality measures.

5.2 Construction Manager

  • Supervise and control site works.
  • Coordinate with QA/QC, site team, and foremen.
  • Approve WIRs before submitting to the Consultant.

5.3 Site Engineer

  • Implement method statement as per project specs and drawings.
  • Monitor progress and coordinate with QA/QC and Safety Engineers.
  • Ensure revised information is communicated to the foremen.

5.4 QA/QC Engineer (MEP)

  • Monitor site work compliance with drawings and specs.
  • Raise MIRs/WIRs and perform quality tests.
  • Coordinate inspections with the Consultant.

5.5 Site Foreman

  • Execute daily work and manage resources.
  • Submit daily progress reports.
  • Report unforeseen incidents immediately.

5.6 Safety Officer

  • Enforce HSE plan and site safety regulations.
  • Provide training and inspections.
  • Ensure PPE use, barricades, and lighting.

5.7 Store Keeper

  • Manage safe and organized storage of materials.
  • Coordinate with QA/QC for material receiving.

6.0 EQUIPMENT

  • Tool Box
  • Measuring Tape
  • Spirit Level
  • Pipe Cutting & Threading Machine
  • Step Ladder, Scaffolds, and Platforms
  • Torque Wrench
  • Electric Drill, Welding & Grinding Machines
  • Solvent Cement
  • Water Level Marker
  • Pressure Gauge
  • Hammer

7.0 PROCEDURE

7.1 General Requirements

  • Use only approved materials and inspect upon delivery.
  • Installation by qualified personnel following specifications.
  • MIR must be approved before installation.

7.2 Material Delivery & Storage

7.2.1 Delivery

  • Transport in covered packaging to prevent damage.
  • Handle carefully; avoid dropping or dragging.

7.3.1 Storage

  • Store indoors, protected from weather.
  • Keep equipment in original packaging until needed.

7.4 Installation Sequence

7.4.1 Safety

  • Follow HSE regulations.
  • Provide toolbox talks before work.
  • Use proper PPE and ensure safe access.

7.4.2 Pre-Installation

  • Confirm all installations and tests are approved.
  • Ensure civil works clearance.
  • Use approved shop drawings only.
  • Check for service clashes.

7.4.3 Installation Procedure

7.4.3.1 General System Description

  • Install as per NFPA 13 and manufacturer guidelines.
  • Sprinklers activate automatically during fire due to heat.

7.4.3.2 Detailed Installation

7.4.3.2.1 Sprinkler Heads

  • Install as per approved drawings.
  • Hand-tighten, then use a wrench.
  • Install escutcheon plates correctly.
  • Ensure proper alignment and spacing.

7.4.3.2.2 Butterfly Valves

  • Install where accessible.
  • Ensure proper valve support.
  • Do not force valve closed; inspect for debris.
  • Integrate fire alarm connections.

7.4.3.2.3 Flow Switches

  • Mount on horizontal (preferably top) or vertical pipes.
  • Drill hole as per manufacturer specs.
  • Ensure vane moves freely inside the pipe.
  • Connect to the fire alarm panel.

7.4.4 Testing & Commissioning

7.4.4.1 Visual Inspection & Testing

  • Verify hydrostatic testing is completed.
  • Ensure proper pipe support and equipment installation.

7.4.4.1.1 Flushing

  • Flush all risers before connecting sprinklers.
  • Use clean water and repeat if necessary.
  • Drain flushed water safely.
  • Conduct hydrostatic test afterward.

7.4.4.2 Commissioning

  • Calibrate all instruments before use.
  • Ensure all installations and supports are approved.
  • Pressurize the system using fire pumps.
  • Check for leaks and proper pressure on all floors.
  • Keep the system under observation for 24 hours.
  • Simulate fault and fire alarms using drain valves.
  • Verify water throw of hose reels (minimum 6m range).
  • Place fire pumps in auto mode post-commissioning.

8.0 ATTACHMENTS

  • Installation Check Sheet
  • Fire Fighting Piping Testing Sheet
  • Testing & Commissioning Checklist
  • Risk Assessment
Add a heading (1)

Method Statement for the installation, Testing & Commissioning of wet chemical fire suppression system for kitchen Hoods.

1.0 PURPOSE:

This method statement covers the nature, type of work & application of the Installation, Testing & Commissioning of Wet Chemical Fire Suppression System for Kitchen Hoods for the project as mentioned in the Approved Shop Drawings & project specifications.

2.0 SCOPE:

Supply, Installation, Testing & Commissioning of Wet Chemical Fire Suppression System for Kitchen Hoods so as to ensure that the job execution complies with project requirements as indicated in the Approved Shop Drawings of Fire Protection System and complies with project specifications enable to serve for its intended purpose to the satisfactory level of the client.

3.0 REFERENCES:

  • Latest Approved shop drawings for the required and applicable areas for Fire Protection System.
  • Specifications
  • NFPA Standard
  • UL 300 Standards
  • Project Quality Plan

4.0 DEFINITIONS:

  • Main Contractor           :
  • MEP Contractor           :
  • PQP                             : Project Quality Plan
  • PSP                              : Project Safety Plan
  • QCP                             : Quality Control Procedure
  • HSE                             : Health, Safety and Environment
  • MS                               : Method Statement
  • ITP                               : Inspection Test Plan
  • QA/QC                        : Quality Assurance / Quality Control Engineer.
  • WIR                             : Inspection and Test Request
  • MIR                             : Material Verification Request
  • MAR                            : Material Approval Request
  • UPVC Class E              : Ultra polyvinyl chloride Class E
  • UPVC                          : Ultra polyvinyl chloride
  • HDPE                          : High density polyethylene

5.0 RESPONSIBILITIES:

Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:

  • Project Manager
  • Construction manager
  • QA/QC Engineer
  • Site Engineer
  • HSE officer
  • SK

5.1 Project Manager

  • The work progress shall be carried out as per planned program and all the equipment’s required to execute the works shall be available and in good condition as per project planned.
  • Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.
  • Project Manager is the overall responsible for the project in terms of work execution, safety, planning & quality. The Project Manager will maintain the planning progress and coordination of works with the main contractor.

5.2 Construction Manager

  • Construction Manager is responsible to supervise and control the work on site.
  • Coordinating with QA/QC Engineers, Site Team & Foremen for all activities on site.
  • Control and sign all WIRs before issuing to Consultant approval.

5.3 Site Engineer

  • The method of statement to the system shall be implemented according to the Consultant project specifications and approved shop drawings.
  • Provision of all necessary information and distribution of responsibilities to his Construction team.
  • The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.
  • The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.
  • The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the Inspection for the finished works.
  • He will ensure the implementation of any request that might be raised by the Consultant.
  • Efficient daily progress shall be obtained for all the equipment and manpower.
  • He will engage in the work and check the same against the daily report received from the Foremen.
  • The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.

5.4 QA/QC Engineer (MEP):

  • The monitoring of executions of works at site and should be as per the approved shop drawings and project specifications & material approval.
  • Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
  • He will follow and carried out all the relevant tests as per project specifications.
  • Obtain the required clearance prior to Consultant’s inspections.
  • Should acquire any necessary civil works clearances and coordination.
  • One who will assist the Consultant Engineer/ Inspector during Inspections.

5.5 Site Foreman

  • The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.
  • Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
  • Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
  • Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.

5.6 Safety Officer

  • The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.
  • The implementation of safety measures is adequate to maintain a safe working environment on the work activity.
  • Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.
  • The site is maintained in a clean and tidy manner.
  • Ensure only trained persons shall operate the power tools.
  • Ensure all concerned personals shall use PPE and all other items as required.
  • Ensure adequate lighting is provided in the working area wherever required.
  • Ensure high risk elevated areas are provided with barricade, tape, safety nets and with ladders.
  • Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
  • Ensure safe access to site work at all times.

 5.7 Store Keeper (SK)

  • Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
  • One who will acknowledge the receiving of materials at site in coordination with QA/QC & concerned Engineer.

6.0 EQUIPMENTS:

Following tools shall be arranged before starting the job.

  1. Tool Box
  2. Measuring Tape
  3. Hack Saw Blade
  4. Spirit Level
  5. Electric Drill Machine
  6. Step Ladders
  7. Excavator
  8. Solvent Cement (if required)
  9. Electric welding machine. (if required)
  10. Crimping Tool
  11. Wire Cutter
  12. Screw Drivers

7.0 PROCEDURE:

7.1 General Requirements

  • All the materials received at site shall be as per the approved technical material submittal for Wet Chemical Fire Suppression System for Kitchen Hoods to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc, should be reported to the supplier for rectification or replacement & to be removed from site immediately.
  • All construction/inspections/testing works shall be carried out in accordance with specifications & to be done by qualified Mechanical Engineers and shall be checked and approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
  • Contractor has to clarify the procedure for material delivery to the site through consultant Engineer at site.

  7.2 Handling & Storage

 7.2.1  Handling

  • During transportation ensure that the materials are in a box or at least covered with plastic. Do not drop the materials especially on hard surfaces. This is particularly important as the materials might be broken, damaged & cause injuries to personnel.
  • Where ever possible the loading and offloading of the equipment & its component shall be carried out by hand.
  • When required or necessary, forklift shall be used in unloading the materials.

7.2.2    Storage

7.2.2.1 Storage on site

  • Wet chemical supplied / delivered shall be stored in the original closed shipping container supplied by the manufacturer. These containers shall not be opened unless otherwise instructed by the Consultant.
  • Wet chemicals supplied/ delivered shall be maintained within the manufacturer’s recommended temperature range.

7.3 Sequence of Installation, Testing & Commissioning.

7.3.1 Safety

  • All site safety rules & regulations shall be complied with.
  • Supervisors will deliver tool box talks, relevant to this installation, to all operatives involved in the installation, and shall be recorded.
  • All operatives will be equipped with minimum personnel protective equipment; hard hat, safety boots, safety glasses.
  • The persons using cleaning fluid and solvent cement have to wear hand gloves.
  • All operatives shall fully understand the method of installing the abovementioned system.

7.3.2 Pre- Installation Procedure

  • Before commencement of installation activity, the supervisor must ensure that:
  • Permission to start or Civil Clearances prior to installation has been given by the main contractor.
  • Materials have been inspected & approved by the Engineer during the delivery via MIR.
  • All relevant Shop drawings for intended for the system in relevance to the area of use have been approved by the Consultant.
  • Necessary openings in the floor (if required) are provided as per the approved builders work drawing.
  • Scaffolding/ ladders if necessary & required for installations are correctly built, safe & suitable for the purpose.
  • Floor Finish level and finish data are available to coordinate with all the elevations & distances required in the installations.

7.3.3 Installation Procedure

  • Ensure the correct type and model of the material as per the approved material submittal.
  • If necessary or required, mock-up will be installed and approved by the Consultant prior to further installations.
  • Ensure that all pipe works/ duct works has been completed, tested & approved by the Consultant.
  • Mark the locations for the cylinders, manual pull stations & pipe routings as per approved shop drawings & support details.
  • Install the Wet Chemical Fire Suppression System at the right location as per Approved drawings.
  • For any discrepancies on the distances & elevations as per the approved drawings shall be marked “red line” on the drawings & shall be incorporated in the as-built drawings.
  • Fix supports & brackets in a vertical position as per support details in the approved working drawing or as recommended by the manufacturer. Ensure that all fixings are secure & durable to hold the cylinder.
  • Install the valve assemblies in an upright position. A shelf bracket is required for use with the cylinder & valve assembly.
  • Recheck the position, distance & elevations of installed brackets & supports.
  • Appropriate holes shall be drilled on the hood for pipe entry, nozzle dropping & plenum entry.
  • Piping supports shall be fixed to the surface of the hood using the approved material for threaded rods, nuts, washers & clamps.
  • Pipes shall be cut & threaded as per the dimensions required.
  • Fusible links along with the housing kit shall be installed & used for each applications as well as one in every exhaust duct.
  • Stainless steel rope shall be connected inside the pipe between the fusible links & cylinders & also from the manual pull station to cylinder.
  • Cable shall be pulled from the cylinder control head to the Fire Alarm Panel.
  • Appropriate terminations shall be done on the cylinder control head (Normally Open/ Normally Close Terminals) as well as on the Fire Alarm Panel.

7.3.4 Testing & Commissioning

  • Upon completion of Installation, the system shall be tested in accordance to the specification & manufacturer’s recommendation & all tests shall be approved by the Consultant thru the Testing & Commissioning Procedures as follows:
  • Check the installation of the cylinder as per the approved locations, elevations & distances stated in the approved shop drawings.
  • Check all supports if properly & correctly installed as per the approved Support Details or Manufacturer’s Recommendations.
  • Check installation of Control Head & Control Valve Assembly.
  • Check installation of Remote Release Pull Station.
  • Check the fusible links if properly fitted with the required clearance.
  • Check the pipes are supported & nozzles are positioned properly.
  • Check the actuation hose is connected between control head and valve.
  • Ensure that the control valve is removed from the cylinder.
  • Install the test cartridge inside the control head.
  • Cut the “S” hook from the last fusible link.
  • Ensure that the control valve is operated.
  • Remove the empty test cartridge and reset the control valve.
  • Replace the “S” hook and reset the control head.
  • Remove the safety pin & operate the remote release pull station.
  • Ensure Control mechanism is operated.
  • Reset the control head.
  • Install one cartridge inside the control head & fix the control valve on the cylinder.

8.0 ATTACHMENTS:

  • Inspection & Test Plan                                                                      
  • Installation Check Sheet                                             
  • Testing & Commissioning Check Sheet             
  • Risk Assessment                    

Power Factor Calculator Online

KW / KVA / PF Calculator

Power Factor = kw/kva

1. kW (Kilowatts) Calculation

To calculate kW (real power), use the formula:

kW = kVA × Power Factor (pf)

Where:

  • kVA is the apparent power (in kilovolt-amperes)
  • Power Factor (pf) is the ratio of real power to apparent power (a value between 0 and 1)

2. kVA (Kilovolt-Amperes) Calculation

To calculate kVA (apparent power), use the formula:

kVA = kW / Power Factor (pf)

Where:

  • kW is the real power (in kilowatts)
  • Power Factor (pf) is the ratio of real power to apparent power (a value between 0 and 1)

3. Power Factor (pf) Calculation

To calculate the Power Factor (pf), use the formula:

Power Factor (pf) = kW / kVA

Where:

  • kW is the real power (in kilowatts)
  • kVA is the apparent power (in kilovolt-amperes)

Power, Current, Voltage Calculator

Electrical Calculator

Ohm’s Law (Voltage, Current, and Resistance)

The relationship between voltage, current, and resistance is given by:

V = I × R

Where:

  • V is the voltage (Volts)
  • I is the current (Amps)
  • R is the resistance (Ohms)

Power Formula (Voltage, Current, and Power)

The relationship between power, voltage, and current is:

P = V × I

Where:

  • P is the power (Watts)
  • V is the voltage (Volts)
  • I is the current (Amps)

Power with Resistance (Using Ohm’s Law)

The power can also be calculated using resistance:

P = I² × R

Or:

P = V² / R

Where:

  • P is the power (Watts)
  • V is the voltage (Volts)
  • I is the current (Amps)
  • R is the resistance (Ohms)

Method Statement For Installation of Water Booster Pumps:

1.0 PURPOSE:

This method statement is applicable for the Installation of Water Booster Pumps for the project as mentioned in the Specifications & Approved Shop Drawings.

2.0 SCOPE:

This method Statement shall cover the Supply & Installation of Water Booster Pumps in line with project requirements as indicated in the Approved Shop Drawings & specifications.

3.0 REFERENCES:

  • Latest Approved shop drawings intended for the Water Booster Pumps
  • Specifications
  • Project Quality Plan
  • Project HSE Plan
  • Material Approval

4.0 DEFINITIONS:

  • PQP                             : Project Quality Plan
  • PSP                              : Project Safety Plan
  • HSE                             : Health, Safety and Environment
  • MS                               : Method Statement
  • ITP                               : Inspection Test Plan
  • QA/QC                        : Quality Assurance / Quality Control Engineer.
  • WIR                             : Inspection Request
  • MIR                             : Material Inspection Request
  • UPVC Class E              : Ultra polyvinyl chloride
  • UPVC                          : Ultra polyvinyl chloride
  • HDPE                          : High density polyethylene

5.0 RESPONSIBILITIES:

Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:

  • Project Manager
  • Construction manager
  • QA/QC Engineer
  • Site Engineer
  • HSE officer
  • SK

5.1 Project Manager

  • The work progress shall be carried out as per planned program and all the equipment’s required to execute the works shall be available and in good condition as per project planned.
  • Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.

5.2 Construction Manager

  • Construction Manager is responsible to supervise and control the work on site.
  • Coordinating with QA/QC Engineers, Site Team & Foremen for all activities on site.
  • Control and sign all WIRs before issuing to Consultant approval.

5.3 Site Engineer

  • The method of statement to the system shall be implemented according to the Consultant project specifications and approved shop drawings.
  • Provision of all necessary information and distribution of responsibilities to his Construction team.
  • The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.
  • The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.
  • The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the Inspection for the finished works.
  • He will ensure the implementation of any request that might be raised by the Consultant.
  • Efficient daily progress shall be obtained for all the equipment and manpower.
  • He will engage in the work and check the same against the daily report received from the Foremen.
  • The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.

5.4 QA/QC Engineer (MEP):

  • The monitoring of executions of works at site and should be as per the approved shop drawings and project specifications.
  • Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
  • He will follow and carries out all the relevant tests as per project specifications.
  • Obtain the required clearance prior to Consultant’s inspections.
  • Should acquire any necessary civil works clearances and coordination.
  • QA/QC Engineer will assist the Consultant Engineer/ Inspector during Inspection.
  • Site Foreman
  • The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.
  • Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
  • Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
  • Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.

5.6 Safety Officer

  • The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.
  • The implementation of safety measures is adequate to maintain a safe working environment on the work activity.
  • Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.
  • The site is maintained in a clean and tidy manner.
  • Ensure only trained persons shall operate the power tools.
  • Ensure all concerned personals shall use PPE and all other items as required.
  • Ensure adequate lighting is provided in the working area at night time.
  • Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders.
  • Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
  • Ensure safe access to site work at all times.

            5.7 Store Keeper (SK)

  • Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.
  • One who will acknowledge the receiving of materials at site in coordination with QA/QC & concerned Engineer.

6.0 EQUIPMENTS:

Following tools shall be arranged before starting the job.

  1. Tool Box.
  2. Measuring Tape.
  3. Hack Saw Blade
  4. Spirit Level
  5. Electric Drill Machine
  6. Step Ladders
  7. Threading Machine
  8. Solvent Cement
  9. Electric welding machine. (if required)
  10. Torque Wrench
  11. Ammeter
  12. Digital Multimeter
  13. Pressure Gauge

7.0 PROCEDURE:

Work Sequence/Procedure

7.1 General Requirements

  • All the materials received at site shall be as per the approved technical material submittal and Water Booster Pump set to be inspected upon receipt & approved by the engineer prior in proceeding with the installation through MIR. Any discrepancies, damages etc, should be reported to the supplier for rectification or replacement & to be removed from site immediately.
  • All construction/inspection/testing works shall be carried out in accordance with the specifications & to be done by qualified Mechanical Engineers and shall be checked and approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
  • Contractor has to clarify the procedure for material delivery to the site through consultant Engineer at site.

7.2        Handling

7.2.1     Material Transport/ Delivery

  • During transportation ensure that the equipment & its components (if any) are delivered in a shipping package and or shall be at least in a box covered with plastic. Extra care in unloading the equipment is required to avoid scratching or denting of finished surfaces of the Pumps & Frames.
  • Where ever possible the loading and offloading of the Water Booster Pumps shall be carried out by hand.
  • When required or necessary, forklift shall be used in unloading the materials.
  • Equipment shall not be dropped onto hard surfaces & should not be dragged along the ground.

7.3   Storage

 7.3.1 Storage on Site Store

  • To ensure that deterioration of Water Booster Pumps does not occur during storage, it is recommended to store the pumps & its components in sheltered conditions that are protected from weather elements and accidental damage.
  • Water Booster Pumps & its components shall be protected with plastic or cardboard and the area shall be barricaded with warning signs.

7.4 Sequence of Installation for Water Booster Pumps:

7.4.1 Safety

  • All site safety rules & regulations shall be complied with.
  • Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the installation, testing & commissioning and shall be recorded.
  • All operatives will be equipped with minimum personnel protective equipment; hard hat, coveralls, safety boots, safety glasses.
  • The persons using cleaning fluid and solvent cement have to wear hand gloves.
  • Ensure that all operatives fully understand the method of these activities.

7.4.2 Pre- Installation Procedure

  • Before commencement of installation activity, the supervisor must ensure that:
  • Delivered Booster Pumps Set have been inspected & approved via MIR by the consultant prior to installation at site.
  • Relevant documents or certificates shall be presented at the time of inspection if required by the Consultant.
  • Permission to start or Civil Clearances prior to installation has been given by the main contractor.
  • All relevant Shop drawings for the installation of Water Booster Pumps shall be available & approved by the consultant. No installation shall be done without Approved Shop Drawings.
  • Installation activities shall only commence when all associated works by the Civil such as clearing of work place, construction of concrete plinth, water proofing, painting of walls/ floor etc. have been verified & completed.
  • Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in charge at site.
  • Inspect the relevant area for any possible clashes with other services.
  • Pumps shall be moved to the work area in a safe manner and shall not block access/ egress from the site with the help of a 3 ton pick- up and or a fork lift.

7.4.3 Installation Procedure

  • Prior to installation, ensure that the data on the name plate matches with the required system data i.e. operating voltage, frequency & pump liquid temperature etc. MIR of the Water Booster Pumps should be approved by the Consultant.
  • Prior to placing the Water Booster Pumps Set in concrete plinth, make sure that the anchoring bolts are matching with the Pump steel base anchoring hole alignment.
  • Lay-out, marked & drill the location of the anchoring bolts on the concrete plinth.
  • Each pump shall be mounted on a neoprene rubber pad concrete.
  • Carefully place the Water Booster Pumps Set into the plinth. Check proper alignment and level by the use of a Torque Wrench.
  • Place the nuts with one flat and lock washer, tight the nuts up to the required torque.
  • After completion of setting-out of the Water Booster Pumps, lay-out and fabricate the suction & discharge piping and supports.
  • Install the fabricated pipes and fittings along with the valves, flexible connectors & strainers as per the approved shop drawings.
  • After completion of installation, raise an inspection request thru WIR to the Consultant for acceptance or Approval. Keep record for reference.
  • Once installation has been accepted & approved by the Consultant, provide covering material to the Installed Water Booster Pump to avoid entry of dirt and dust. Remove all covers when termination of cables will start.
  • Testing & Commissioning shall commence after final approval of the installation by the consultant.

8.0 ATTACHMENTS:

  • Inspection & Test Plan                                      
  • Installation Check Sheet                               
  • Risk Assessment

Method Statement For Installation Of Sump Pump:

1.0 PURPOSE:

The purpose of generating this method statement is to define the procedure step by step to implement the correct practices for Installation of Sump Pump through the guidelines contained herein so as to ensure that the job execution complies with the requirements of contract specification and serves the intended function to satisfactory level.in all applicable areas for the project.

2.0 SCOPE:

This method statement covers all processes related to Installation of Sump pump.

This procedure is to be read in conjunction with the relevant ITP, outlining the responsibility and the quality verification to be performed by various parties.

3.0  REFERENCES:

  • Latest Approved shop drawings for the required and applicable areas for plumbing system.
  • Specifications
  • Project Quality Plan
  • Material Submittals

4.0  DEFINITIONS:

PQP                                        : Project Quality Plan

PSP                                         : Project Safety Plan

QCP                                        : Quality Control Procedure

HSE                                        : Health, Safety and Environment

MS                                          : Method Statement

ITP                                         : Inspection Test Plan

QA/QC                                   : Quality Assurance / Quality Control Engineer.

WIR                                       : Inspection and Test Request

MIR                                       : Material Inspection Report

5.0  RESPONSIBILITIES:

  • Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at relevant steps in the procedure:
  • Project Manager
  • Construction manager
  • QA/QC Engineer
  • Site Engineer
  • HSE officer
  • SK

5.1 Project Manager

  • The work progress shall be carried out as per planned program and all the equipment’s required to execute the works shall be available and in good condition as per project planned.
  • Specific attention is paid to all safety measures and quality control in coordination with Safety Engineer and QA/QC Engineer and in line with PSP and PQP.

5.2 Construction Manager

  • Construction Manager is responsible to supervise and control the work on site.

5.3 Site Engineer

  • The method of statement to the system shall be implemented according to the Consultant project specifications and approved shop drawings.
  • Provision of all necessary information and distribution of responsibilities to his Construction team.
  • The work progress shall be monitored in accordance with the planned work program and he will provide reports to his superiors.
  • The constant coordination with the Safety Engineer to ensure that the works are carried out in safe working atmosphere.
  • The constant coordination with the QA/QC Engineer for any works to be carried out and initiate for the Inspection for the finished works.
  • He will ensure the implementation of any request that might be raised by the Consultant.
  • Efficient daily progress shall be obtained for all the equipment and manpower.
  • He will engage in the work and check the same against the daily report received from the Foremen.
  • The passage of all the revised information to the Foremen and ensure that it’s being carried out properly.

5.4 QA/QC Engineer (MEP):

  • The monitoring of executions of works at site and should be as per the approved shop drawings and project specifications.
  • Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the Consultant.
  • He will follow and carried out all the relevant tests as per project specifications.
  • Obtain the required clearance prior to Consultant’s inspections.
  • Should acquire any necessary civil works clearances and coordination.

5.5 Site Foreman

  • The carrying-out of work and the proper distribution of all the available resources in coordination with the Site Engineer on a daily basis.
  • Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.
  • Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
  • Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.

5.6 Safety Officer

  • The implementation of all safety measures in accordance with the HSE plan and that the whole work force is aware of its proper implementation.
  • The implementation of safety measures is adequate to maintain a safe working environment on the work activity.
  • Inspection of all the site activities and training personnel in accident prevention and its proper reporting to the Construction Manager and the Project Manager.
  • The site is maintained in a clean and tidy manner.
  • Ensure only trained persons shall operate the power tools.
  • Ensure all concerned personals shall use PPE and all other items as required.
  • Ensure adequate lighting is provided in the working area at night time.
  • Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with ladders also to Ensure of provided warning tapes in manhole places.
  • Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
  • Ensure safe access to site work at all times.

5.7 Store Keeper (SK)

  • Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.

6.0  EQUIPMENT:

  • Tool box
    • Measuring tape
    • Marker
    • Wood-saw
    • Half round file
    • Wooden half round file
    • Hack-saw frame
    • Drill machine
    • Concrete bit
    • Moveable Hook/ Pulley
    • Anchor punch
    • Marking line-dori
    • Screw driver (flat & set)
    • Fix spanner (4mm to 32 mm)
    • Adjustable spanner
    • Sprite level
    • Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest, and safety gloves to ensure maximum ability of safe work and dust mask when required.

7.0  PROCEDURE:

7.1 Safety

  • Ensure only trained persons shall operate the power tools.
  • Ensure all concerned personnel shall use PPE (Personal Protective Equipment) and all other items as required.
  • Ensure adequate lighting is provided in the working area at night time.
  • Ensure service area/work area openings are provided with barricade, tape, and safety nets.

7.2 Work Sequence And Methodology

  • Check all material delivered to site is inspected properly by QA/QC Engineer and check if it is stored properly as per manufacturer’s recommendations.
  • MIR shall be raised for the inspection of the delivered sump pumps on site Consultant approval.
  • Work shall be carried out by the site staff under strict supervision and guidance of the concerned Supervisors / Foremen / Engineers.
  • The QA/QC Engineer shall check the Installations as per Check list items.
  • WIR shall be prepared by QA/QC Engineer and will be submitted to Consultant for their inspection and approval.
  • QA/QC Engineer shall coordinate with other Contractors and arrange inspection for installation to the Consultant Engineer.
  • QA/QC Engineer is responsible for all installation activities for getting the work inspected / approved by Consultant Engineer.

7.3 Handling and Storage

  • On receipt of sump pumps at site, necessary precautions shall be taken for unloading, shifting, and storage as follows:
  •  
  • Any Sump pumps & accessories deliver at site shall be carefully off-loaded by deploying necessary manpower in such a way that no damage shall caused to it.
  • All pumps & accessories shall be inspected, handled and stored properly upon receipt at site and after consultant approval for the material.
  • Pumps and accessories shall be stored in a place free of water, dust and adequately covered to avoid any kind of damages.
  • Pump shall be transported to work place using adequate manpower.
  • Any discrepancies, damage, and etc. found to the materials will be notified and reported to QA/QC Engineer and Project Engineer for further action.
  • Materials found not suitable for site use should be removed from site immediately.
  • All materials to be used shall be as per consultant MAR procedure and approval.

7.4 Installation of the sump pump

  • Obtain clearance from the civil work prior installation of sump pump.
  • Make sure that Sump pump material inspection is done.
  • Sump pit depth should be checked and as per approved shop drawings & builder work drawings.
  • Mark the pump location matching with proper guide rail location as per approved shop drawings and builder work drawings.
  • Install the pump as per specification and approved shop drawings.
  • Confirming to the matching line of flange install the guide rail and supporting chain.
  • Ensure all support as per manufacturer recommendation and approved shop drawings.
  • All Piping to be done in accordance to approved drawings and pump out let size.
  • Gate valve and PRV to be install properly.
  • All valves and major fittings to be supported properly.
  • Install relevant float switches.
  • Install the Control panel for the sump pump as per approved shop drawings and manufacturer recommendation.
  • As per manufacturer’s recommendation, pumps shall be lifted with the cabtyre cable lifted slightly. Secure it to the hook. A hook must be prepared in advance by placing it on the frame of a manhole. Refer to attached Manufacturer’s recommendation.
  • Raise inspection for Consultant approval after completion of the work.

7.5 Connections

  • Connection of the piping will be as per approved shop drawings and manufacturer recommendation indicate general arrangement of piping, fittings, and specialties.
  • Install piping adjacent to equipment to allow service and maintenance.

8.0 ATTACHMENTS

  • Inspection & Test Plan                          
  • Check List                                                
  • Risk Assessment