1. Scope of Work
This method statement covers the procedures, responsibilities, and quality requirements for the installation, testing, and commissioning of domestic cold and hot water supply piping systems for the project, ensuring compliance with applicable codes, standards, and approved project specifications.
2. References
- Project Specifications
- Local Plumbing Code
- International Plumbing Code (IPC)
- ASME B31.9 – Building Services Piping
- Manufacturer’s Installation Guidelines
- Approved Shop Drawings
3. Responsibilities
- Project Manager: Overall supervision and resource management.
- Site Engineer: Execution as per approved drawings and specifications.
- QA/QC Engineer: Inspection and quality control.
- Safety Officer: Ensure safety compliance during all activities.
- Foreman/Plumber: Direct execution of the work.
4. Materials and Tools
Materials:
- PPR, PEX, or Copper Pipes (as per approved material)
- Pipe Fittings (elbows, tees, couplings, reducers)
- Valves (Gate, Ball, Check, Mixing)
- Pipe Supports and Clamps
- Insulation for hot water lines
- Identification tags and labels
Tools:
- Pipe cutter and reamer
- Welding or fusion machines (for PPR/PEX)
- Torque wrenches
- Pressure testing pump (manual/digital)
- Thermometers and pressure gauges
- PPE and safety equipment
5. Installation Procedure
5.1 Pre-Installation Checks:
- Verify material approvals and delivery conditions.
- Ensure all tools and equipment are calibrated and in working condition.
- Confirm site readiness and access.
5.2 Marking and Layout:
- Mark the pipe routing as per the approved shop drawings.
- Confirm locations of fixtures, valves, and access points.
5.3 Pipe Installation:
- Cut pipes to required lengths, ensuring burr-free edges.
- Join pipes using the appropriate technique:
- PPR: Fusion welding
- PEX: Crimping or expansion fittings
- Copper: Soldering or brazing
- Ensure pipe slopes (if applicable) for drainage or venting.
- Provide supports/clamps at manufacturer-recommended intervals.
- Install valves and accessories as per drawings.
5.4 Insulation and Identification:
- Apply insulation to all hot water lines.
- Label all pipes clearly for cold/hot water direction and purpose.
6. Testing Procedure
6.1 Hydrostatic Pressure Test:
- Cap all open ends and install pressure gauge.
- Fill the system with water and remove air through vents.
- Test cold water lines at 1.5 times working pressure (typically 10 bar or as specified).
- Test hot water lines similarly.
- Maintain pressure for at least 2 hours.
- Monitor for pressure drop and visible leaks.
6.2 Functional Testing:
- Open valves and allow water flow to all fixtures.
- Verify flow rate, pressure, and temperature.
- Check operation of mixing valves and temperature control devices.
7. Commissioning
- Ensure all systems are flushed with clean water.
- Disinfect the water supply lines using an approved disinfectant.
- Remove airlocks by purging all outlets.
- Set and calibrate thermostatic mixing valves if used.
- Ensure hot water temperature settings comply with safety requirements (typically 50-55°C).
- Record commissioning data and submit for approval.
8. Safety Considerations
- Ensure all workers wear appropriate PPE.
- Use lock-out/tag-out procedures for pressurized systems.
- Handle fusion/welding equipment with care.
- Avoid water spillage to prevent slips and falls.
9. Quality Assurance and Documentation
- All installations shall be inspected by the QA/QC Engineer before closing any ceiling/floor.
- Submit inspection and test reports for:
- Pressure testing
- Disinfection
- Final commissioning
- Maintain as-built records and O&M manuals.
10. Attachments
- Pressure Test Certificate Template
- Inspection Checklist
- Manufacturer’s Datasheets
- Material Submittals
- As-Built Drawings
Add a Comment