Method Statement for Fire Pump Installation, Testing, and Commissioning:

1. Purpose of Fire Pump Method Statement

  • Define step-by-step procedures for fire pump installation, testing, and commissioning.
  • Ensure compliance with contract specifications and approved shop drawings.
  • Guarantee reliable operation for all designated areas in the project.

2. Scope of Work

  • Covers complete process of:
    • Installation of fire pump sets
    • Testing procedures
    • Commissioning protocols
  • Linked with relevant ITP and quality verification steps.

3. Reference Documents

  • Approved Fire Fighting System shop drawings
  • Project Specifications
  • Project Quality Plan (PQP)

4. Key Definitions

  • PQP – Project Quality Plan
  • PSP – Project Safety Plan
  • QA/QC – Quality Assurance/Quality Control
  • ITP – Inspection and Test Plan
  • WIR – Work Inspection Request
  • MIR – Material Inspection Record

5. Responsibilities

5.1 Project Manager

  • Ensure timely progress and equipment readiness.
  • Oversee safety and quality coordination.

5.2 Construction Manager

  • Supervise on-site activities.
  • Manage coordination, reporting, and approvals.

5.3 Site Engineer

  • Lead installation as per drawings and specs.
  • Coordinate with QA/QC and Safety teams.

5.4 QA/QC Engineer

  • Monitor installations for quality compliance.
  • Handle inspections, WIRs, and MIRs.

5.5 Site Foreman

  • Distribute resources and manage day-to-day work.
  • Prepare daily reports and ensure safety compliance.

5.6 Safety Officer

  • Enforce HSE measures.
  • Conduct inspections and ensure PPE use.

5.7 Store Keeper

  • Manage storage and delivery of materials.
  • Coordinate with QA/QC during material reception.

6. Tools and Equipment Required

  • Measuring Tape, Drill Machine, Threading Machine
  • Chain Block, Forklift, Spirit Level
  • Digital Multimeter, Ammeter, Pressure Gauges
  • Safety gear: helmets, gloves, vests, goggles

7. Procedure

7.1 Safety Protocols

  • Use trained personnel only.
  • Wear proper PPE.
  • Provide adequate lighting and area barricades.
  • Permit-controlled access.

7.2 Installation Procedure

  • Transport pump set to room using forklift.
  • Fix anchor bolts, provide vibration pads.
  • Connect suction/discharge piping and pressure switches.
  • Complete electrical & BMS connections.
  • Raise inspection for consultant approval.

7.3 Testing and Commissioning

7.3.1 Pre-Start-Up Inspection

  • Visual and mechanical checks
  • Secure anchoring and alignment
  • Proper piping and valve connections
  • Confirm electrical wiring and fluid levels

7.3.2 Operation Sequence

Electric Pump

  • Open suction valves
  • Check water filling, air release
  • Run pump, verify direction, monitor current draw

Diesel Pump

  • Check engine parameters: RPM, oil, fuel pressure
  • Confirm relief valve settings and noise levels

7.3.3 Flow Testing

Electric & Diesel Pump

  • Simulate flow using flow meter valves
  • Record pressure and RPM at rated, 150% flow
  • Match results with factory test curves

7.3.4 Automatic Operation Setup

  • Configure pressure switches:
    • Jockey, Electric, Diesel start pressures
  • Switch control panels to AUTO mode

7.3.5 Control Panel Functions

  • Automatic Mode – Fire pump auto-start based on pressure drop
  • Manual Mode – Start via control panel or engine panel
  • Emergency Start – Use handle if control circuit fails

8. Attachments

  • 8.1: Inspection & Test Plan (ITP)
  • 8.2: Installation Checklist
  • 8.3: Testing & Commissioning Checklist
  • 8.4: Risk Assessment