Drainage pipe installation Checklist:

  1. Checklist for Installation & Testing of Drainage Piping System and Accessories
  2. Checklist for Testing of Drainage Piping System

Project Details

Subcontractor:
Contractor:
Section of Work: Plumbing
Location:
Level:
Work Inspection Request (WIR) No.:


Inspection Stages

Setting Out

  • Check Layout:
    Verify layout of the drainage piping system is as per approved shop drawings.
  • Check Level / Depth:
    Ensure the level and excavation depth are according to design and approved drawings.

MEP / Civil Coordination

  • Clearances Check:
    Confirm that there are no service clashes and required clearance is provided.
    Verify clearance approval by the consultant’s civil site team.

Installation Inspection

  1. Material Compliance:
    Ensure all installed materials match the approved material submittals.
  2. Bedding Condition:
    Check that bedding is free from hard protrusions or large stones and is suitable for pipe laying.
  3. Pipe Size Verification:
    Confirm that pipe sizes conform to approved drawings.
  4. Slope and Level Check:
    Verify that the level and slope of the installed pipes meet the approved shop drawing specifications.
  5. Manhole Joint Installation:
    Ensure push-fit joints are correctly installed for all manhole inlets and outlets.
  6. Road Crossing Pipes:
    Confirm that pipes crossing roadways are installed according to approved shop drawings.
  7. Leak Testing:
    All drainage pipes must be tested for leaks.
  8. Pipe End Protection:
    Check that all open pipe ends are sealed to protect against debris during construction.
  9. Concrete Encasement:
    Confirm concrete encasement has been applied where required.
  10. Backfilling Release:
    Ensure pipes are approved and released for backfilling.
  11. Backfilling Execution:
    Check that backfilling is done in accordance with the approved drawings and specifications.

Final Approvals

For Subcontractor QA/QC:

  • Name:
  • Signature:
  • Date:

For Contractor QA/QC:

  • Name:
  • Signature:
  • Date:

For Consultant Representative:

  • Name:
  • Signature:
  • Date:

2- Checklist for Testing of Drainage Piping System

Form No.:
Revision No.: 0
Page: 1 of 1


Project Information

Subcontractor:
Contractor:
Section of Work: Plumbing
Location:
Level:
Work Inspection Request (WIR) No.:


Inspection & Testing Checklist

Stage-wise Verification

  • Stage:
  • Item:
  • Checked by (Subcontractor):
  • Checked by (Contractor):
  • Checked by (Consultant):
  • Date:

Test Details

  • Piping System:
  • Test Pressure:
  • Actual Pressure:
  • Date of Test:
  • Duration of Test:
  • Testing Fluid/Gas:
  • Start Time:
  • Finish Time:
  • Pressure Gauge Number:
  • Calibration Due Date:

Remarks

(Insert any additional observations or issues noted during the test)





Test Results

☐ No leaks were observed during the test duration. Test results are acceptable.
☐ Test results are not acceptable. Rectify leaks and retest.


Sign-Off and Approval

Subcontractor QA/QC

  • Name:
  • Signature:
  • Date:

Contractor QA/QC

  • Name:
  • Signature:
  • Date:

Consultant Representative

  • Name:
  • Signature:
  • Date: