1. 💨 Air Balancing Procedures
A. Fan Coil Units (FCU) Balancing Steps
- Ensure automatic control systems are fully commissioned.
- Perform all pre-commissioning checks.
- Set FCU to specified fan speed.
- Open all diffuser/grille dampers fully.
- Measure initial airflow from all outlets using a flow hood.
- Calculate total measured flow and compare with design flow.
- Identify the index outlet (lowest percentage of flow).
- Keep index outlet damper fully open.
- Adjust other outlets to proportionally match design flow using bolometer.
- As you adjust each outlet, monitor the index outlet for airflow changes.
- Finalize proportional balance at all outlets and record all values.
B. Ventilation / Exhaust Fan Balancing
- Confirm pre-commissioning checks are complete.
- Record fan motor amperage and RPM.
- Ensure fan settings are within manufacturer limits.
- Open all duct dampers (main and branches).
- Measure total airflow using the duct traverse method (target: 105% of design flow).
- Identify the index branch (lowest reading).
- Balance all other branches proportionally, keeping index branch damper open.
- Monitor and measure airflow after each adjustment.
- Finalize the balance and record results.
C. Air Handling Unit (AHU) Balancing
- Set fan speed to deliver total design air quantity.
- Ensure speed does not exceed manufacturer’s limits.
- Open all main, branch, and terminal dampers.
- Measure total fan airflow using duct traverse (target: 105% of design flow).
- Identify index branch and keep damper fully open.
- Balance other branches and terminals proportionally.
- Ensure motor amperage stays within limits.
- Record final measurements:
- Fan RPM
- Motor voltage and current
- Static pressure (entering and leaving the fan)
D. Air Terminal Balancing Procedure
- Use flow hood or bolometer where access is available.
- Use anemometer and calculate velocity × free area if access is restricted.
- Begin balancing at the most remote branch or terminal.
- Identify index terminal (lowest percentage of design flow).
- Adjust adjacent terminals to match the index terminal percentage.
- Continue this process progressively.
- Record all terminal flow rates and ensure totals match sub-branch flow.
- Follow CIBSE Application Guide 3/89 for standards.
E. Stairwell Pressurization Fan Balancing
- Complete all pre-commissioning and interfacing checks.
- Ensure fire alarm integration is functional.
- Open all outlet dampers.
- Measure initial airflow from all terminals (Initial Scan).
- Identify the index outlet (least airflow).
- Keep index damper open and throttle other dampers proportionally.
- Use anemometer to monitor index flow as others are adjusted.
- Record balanced values for all outlets.
- Measure and record pressure difference between floors and stairwells.
2. ❄️ Chilled Water System Balancing
F. Secondary Pump Shut-Off Head Test
- Use a differential pressure gauge to test across suction/discharge points.
- Set all valves (supply, return, and control) to fully open.
- Run pump and temporarily close discharge valve (<1 minute).
- Measure shut-off head and compare with manufacturer data.
- If not matching, create a parallel curve from test data.
- Re-open valve slowly and proceed to full-flow pressure check.
G. Preliminary Flow Rate Check
- With all valves open, measure total actual flow.
- Compare with system design flow.
- Adjust main regulating valve to achieve ~110% of design flow if needed.
H. Proportional Chilled Water Balancing (Main to Terminal)
- Keep DRVs and isolation valves fully open.
- Measure initial flow across heat exchangers and risers.
- Identify index riser (lowest flow).
- Keep index DRV open and throttle other risers proportionally.
- Monitor index percentage rise after each riser adjustment.
- Finalize balance and record flow across all risers.
I. Final Witnessing & Reporting
- Upon successful TAB completion:
- Submit the test report to the consultant.
- Schedule witnessing inspection.
- Ensure documentation includes all final readings and compliance with design specs.
🔍 SEO Keywords to Include:
- Air Balancing Procedure
- Chilled Water Balancing
- HVAC Testing and Commissioning
- AHU & FCU Balancing
- Stairwell Pressurization Testing
- Ventilation System TAB
- Flow Hood Testing
- CIBSE Standard Air Balancing
Add a Comment