🔧 Air and Water Balancing Method Statement for HVAC Systems

1. 💨 Air Balancing Procedures

A. Fan Coil Units (FCU) Balancing Steps

  • Ensure automatic control systems are fully commissioned.
  • Perform all pre-commissioning checks.
  • Set FCU to specified fan speed.
  • Open all diffuser/grille dampers fully.
  • Measure initial airflow from all outlets using a flow hood.
  • Calculate total measured flow and compare with design flow.
  • Identify the index outlet (lowest percentage of flow).
  • Keep index outlet damper fully open.
  • Adjust other outlets to proportionally match design flow using bolometer.
  • As you adjust each outlet, monitor the index outlet for airflow changes.
  • Finalize proportional balance at all outlets and record all values.

B. Ventilation / Exhaust Fan Balancing

  • Confirm pre-commissioning checks are complete.
  • Record fan motor amperage and RPM.
  • Ensure fan settings are within manufacturer limits.
  • Open all duct dampers (main and branches).
  • Measure total airflow using the duct traverse method (target: 105% of design flow).
  • Identify the index branch (lowest reading).
  • Balance all other branches proportionally, keeping index branch damper open.
  • Monitor and measure airflow after each adjustment.
  • Finalize the balance and record results.

C. Air Handling Unit (AHU) Balancing

  • Set fan speed to deliver total design air quantity.
  • Ensure speed does not exceed manufacturer’s limits.
  • Open all main, branch, and terminal dampers.
  • Measure total fan airflow using duct traverse (target: 105% of design flow).
  • Identify index branch and keep damper fully open.
  • Balance other branches and terminals proportionally.
  • Ensure motor amperage stays within limits.
  • Record final measurements:
    • Fan RPM
    • Motor voltage and current
    • Static pressure (entering and leaving the fan)

D. Air Terminal Balancing Procedure

  • Use flow hood or bolometer where access is available.
  • Use anemometer and calculate velocity × free area if access is restricted.
  • Begin balancing at the most remote branch or terminal.
  • Identify index terminal (lowest percentage of design flow).
  • Adjust adjacent terminals to match the index terminal percentage.
  • Continue this process progressively.
  • Record all terminal flow rates and ensure totals match sub-branch flow.
  • Follow CIBSE Application Guide 3/89 for standards.

E. Stairwell Pressurization Fan Balancing

  • Complete all pre-commissioning and interfacing checks.
  • Ensure fire alarm integration is functional.
  • Open all outlet dampers.
  • Measure initial airflow from all terminals (Initial Scan).
  • Identify the index outlet (least airflow).
  • Keep index damper open and throttle other dampers proportionally.
  • Use anemometer to monitor index flow as others are adjusted.
  • Record balanced values for all outlets.
  • Measure and record pressure difference between floors and stairwells.

2. ❄️ Chilled Water System Balancing

F. Secondary Pump Shut-Off Head Test

  • Use a differential pressure gauge to test across suction/discharge points.
  • Set all valves (supply, return, and control) to fully open.
  • Run pump and temporarily close discharge valve (<1 minute).
  • Measure shut-off head and compare with manufacturer data.
  • If not matching, create a parallel curve from test data.
  • Re-open valve slowly and proceed to full-flow pressure check.

G. Preliminary Flow Rate Check

  • With all valves open, measure total actual flow.
  • Compare with system design flow.
  • Adjust main regulating valve to achieve ~110% of design flow if needed.

H. Proportional Chilled Water Balancing (Main to Terminal)

  • Keep DRVs and isolation valves fully open.
  • Measure initial flow across heat exchangers and risers.
  • Identify index riser (lowest flow).
  • Keep index DRV open and throttle other risers proportionally.
  • Monitor index percentage rise after each riser adjustment.
  • Finalize balance and record flow across all risers.

I. Final Witnessing & Reporting

  • Upon successful TAB completion:
    • Submit the test report to the consultant.
    • Schedule witnessing inspection.
    • Ensure documentation includes all final readings and compliance with design specs.

🔍 SEO Keywords to Include:

  • Air Balancing Procedure
  • Chilled Water Balancing
  • HVAC Testing and Commissioning
  • AHU & FCU Balancing
  • Stairwell Pressurization Testing
  • Ventilation System TAB
  • Flow Hood Testing
  • CIBSE Standard Air Balancing