📌 Table of Contents
- Purpose
- Scope
- References
- Definitions
- Roles & Responsibilities
- Tools & Materials
- Step-by-Step Procedure
- Attachments
🎯 1. Purpose
This method statement outlines the complete process for the installation, testing, and commissioning of the Smoke Management System, ensuring full compliance with the approved shop drawings and project specifications.
📍 2. Scope
Covers the procedures and guidelines to be followed for Smoke Management System installation in accordance with project specifications and manufacturer guidelines.
📚 3. References
- Project Quality Plan (PQP)
- Project HSE Plan (PSP)
- Approved Shop Drawings
- Material Approval Requests
- SMACNA, ARI, UL, NEMA, AMCA, BS standards
🔍 4. Definitions
- MS – Method Statement
- WIR – Work Inspection Request
- MAR – Material Approval Request
- FSCS – Firefighter Smoke Control Station
- HOA – Hand Off Auto Module
(Full list retained in original document)
👥 5. Roles & Responsibilities
📌 Project Manager
- Oversee work as per schedule
- Ensure safety & quality coordination
- Ensure availability of tools and equipment
📌 Construction Manager
- Supervise on-site work
- Approve WIRs
- Coordinate with site & QA/QC teams
📌 Site Engineer
- Implement method statement
- Coordinate with QA/QC & Safety
- Monitor daily progress
📌 QA/QC Engineer
- Ensure installation as per drawings/specs
- Raise WIRs/MIRs timely
- Coordinate inspections & ensure clearance
📌 Site Foreman
- Manage daily activities
- Maintain progress reports
- Coordinate with Site Engineer
📌 Safety Officer
- Enforce HSE Plan
- Train staff on safety practices
- Maintain clean & hazard-free environment
📌 Store Keeper
- Manage material receipt & storage
- Ensure material approval & protection
🧰 6. Tools & Materials
- Marker
- Screwdrivers
- Pliers
- Multimeter
- Test Lamp
🛠️ 7. Procedure
🔧 Installation
- Check panel location per approved drawings
- Install FSCS and HOA modules
- Ensure earthing and connection points
- Connect LED/switch controllers using ribbon and communication cables
👀 Visual Inspection
- Confirm all components are installed properly
- Verify alignment with drawings and specs
- Ensure all labels and LEDs are correct
🔍 Pre-Commissioning (Cold Testing)
- Confirm back box, cable markers, labels
- Replace faulty items
- Document checks in pre-commissioning checklist
⚡ Power-Up
- Check 24V DC power and data cables
- Ensure proper polarity and terminations
- Energize FSCS Panel
✅ Testing & Commissioning
- Notify personnel before testing fans (AHU, SPF, LPF, etc.)
- Test damper OPEN/CLOSE buttons and LEDs
- Test ON/OFF/AUTO switches and LED indicators
- Test LAMP switch for LED functionality
👨🔧 Witness Demonstration
- Record results in T&C checklists
- Final documentation and consultant sign-off
📎 8. Attachments
- 📝 Inspection & Test Plan (ITP-6012-0200 Rev.03)
- ✅ Check Sheet (FM-6012-0200 Rev.03)
- ⚠️ Risk Assessment (RA-6012-0200 Rev.03)