Drainage pipe installation Checklist:

  1. Checklist for Installation & Testing of Drainage Piping System and Accessories
  2. Checklist for Testing of Drainage Piping System

Project Details

Subcontractor:
Contractor:
Section of Work: Plumbing
Location:
Level:
Work Inspection Request (WIR) No.:


Inspection Stages

Setting Out

  • Check Layout:
    Verify layout of the drainage piping system is as per approved shop drawings.
  • Check Level / Depth:
    Ensure the level and excavation depth are according to design and approved drawings.

MEP / Civil Coordination

  • Clearances Check:
    Confirm that there are no service clashes and required clearance is provided.
    Verify clearance approval by the consultant’s civil site team.

Installation Inspection

  1. Material Compliance:
    Ensure all installed materials match the approved material submittals.
  2. Bedding Condition:
    Check that bedding is free from hard protrusions or large stones and is suitable for pipe laying.
  3. Pipe Size Verification:
    Confirm that pipe sizes conform to approved drawings.
  4. Slope and Level Check:
    Verify that the level and slope of the installed pipes meet the approved shop drawing specifications.
  5. Manhole Joint Installation:
    Ensure push-fit joints are correctly installed for all manhole inlets and outlets.
  6. Road Crossing Pipes:
    Confirm that pipes crossing roadways are installed according to approved shop drawings.
  7. Leak Testing:
    All drainage pipes must be tested for leaks.
  8. Pipe End Protection:
    Check that all open pipe ends are sealed to protect against debris during construction.
  9. Concrete Encasement:
    Confirm concrete encasement has been applied where required.
  10. Backfilling Release:
    Ensure pipes are approved and released for backfilling.
  11. Backfilling Execution:
    Check that backfilling is done in accordance with the approved drawings and specifications.

Final Approvals

For Subcontractor QA/QC:

  • Name:
  • Signature:
  • Date:

For Contractor QA/QC:

  • Name:
  • Signature:
  • Date:

For Consultant Representative:

  • Name:
  • Signature:
  • Date:

2- Checklist for Testing of Drainage Piping System

Form No.:
Revision No.: 0
Page: 1 of 1


Project Information

Subcontractor:
Contractor:
Section of Work: Plumbing
Location:
Level:
Work Inspection Request (WIR) No.:


Inspection & Testing Checklist

Stage-wise Verification

  • Stage:
  • Item:
  • Checked by (Subcontractor):
  • Checked by (Contractor):
  • Checked by (Consultant):
  • Date:

Test Details

  • Piping System:
  • Test Pressure:
  • Actual Pressure:
  • Date of Test:
  • Duration of Test:
  • Testing Fluid/Gas:
  • Start Time:
  • Finish Time:
  • Pressure Gauge Number:
  • Calibration Due Date:

Remarks

(Insert any additional observations or issues noted during the test)





Test Results

☐ No leaks were observed during the test duration. Test results are acceptable.
☐ Test results are not acceptable. Rectify leaks and retest.


Sign-Off and Approval

Subcontractor QA/QC

  • Name:
  • Signature:
  • Date:

Contractor QA/QC

  • Name:
  • Signature:
  • Date:

Consultant Representative

  • Name:
  • Signature:
  • Date:

Domestic Cold and Hot Water Supply Piping System Checklist:

Content of Checklist:

  1. Water Supply Installation Checklist
  2. Cold Water Piping System (Underground) Checklist
  3. Checklist for Testing of Water Supply Piping System and Accessories:

Ref. No:
Revision No: 0
Page:

Subcontractor:
Contractor:
Section of Work: Water Supply
Location:
Level:
WIR No.:


Stage: Setting Out

  • Verify layout accuracy.
  • Confirm levels with MEP/Civil coordination.
  • Ensure chipping in the wall is completed where necessary.

Stage: Installation

Service Clearances

  • Confirm adequate clearances for services.
  • Ensure approvals from consultant site team (civil) are obtained.

Material and Size Verification

  1. Ensure all materials are as per the approved material submittal.
  2. Verify that pipe sizes match those specified in the approved drawings.

Piping Layout and Components

  1. Ensure all pipes installed inside walls follow the approved shop drawings.
  2. Confirm isolation valves are located as indicated in the approved drawings.
  3. Check that expansion/contraction joints are installed according to approved drawings.
  4. Confirm air vents, with isolation valves, are installed as per approved drawings.
  5. Check for the installation of water hammer arrestors with isolation valves.
  6. Verify PRVs (Pressure Reducing Valves) are installed as per the drawings.
  7. Ensure backflow preventers are installed in accordance with the approved shop drawings.

Testing and Disinfection

  1. Confirm the piping network has been tested for leaks (1.5 times working pressure for 24 hours).
  2. Ensure network disinfection has been carried out using chlorine as per Method Statement Section 7.9.
  3. Verify that water samples (from the network and tank) are submitted to a third-party laboratory (ITL) for quality testing.

Identification and Sealing

  1. Ensure service identification labels are provided on all exposed pipes and inside access doors.
  2. Check that annular spaces between pipes and sleeves are sealed using approved materials.

Approvals and Sign-Off

For Subcontractor QA/QC:
Date: __________
Name: _____________________
Signature: __________________

For Contractor QA/QC:
Date: __________
Name: _____________________
Signature: __________________

For Consultant Representative:
Date: __________
Name: _____________________
Signature: __________________

Project Location: (Specify Location)
Level: Basement
Work Inspection Request (WIR) No.: (Specify WIR No.)
Section of Work: Water Supply


Setting Out Works

  • Check Layout – Ensure layout is as per the approved drawings.
  • Check Level (MEP/Civil) – Confirm that the level is accurate and in compliance with approved elevations.

Installation Checklist

  1. Confirm that pipe sizes and materials match approved specifications and have been inspected and cleared for installation.
  2. Ensure all flanges are clean and free from debris or contaminants before installation.
  3. Verify that puddle flanges are externally painted with two coats of bituminous paint before being integrated into the structure.
  4. Confirm that sleeves are also clean and free from any debris or contaminants prior to installation.
  5. Make sure the entire installation follows approved drawings and maintains the approved invert levels.
  6. Check that puddle flanges are aligned, and the central plate is exactly vertical using a level indicator.
  7. Ensure that sleeves are aligned, and the central plate is exactly vertical using a level indicator.
  8. For puddle flange pipe pieces, ensure that edges are properly prepared and cleaned before welding, and check alignment and position.
  9. Secure the puddle flange with suitable wires to the reinforcement steel to prevent any displacement during concreting.
  10. Perform a final check of the installation before closing the shuttering.

QA/QC Sign-Off

Subcontractor QA/QC:
Name: ____________________
Sign: ____________________
Date: ____________________

Contractor QA/QC:
Name: ____________________
Sign: ____________________
Date: ____________________

Consultant Representative:
Name: ____________________
Sign: ____________________
Date: ____________________

Form No:
Revision No: 0
Page: 1 of 1


Project Details

  • Subcontractor:
  • Contractor:
  • Section of Work: Water Supply
  • Location:
  • Level:
  • WIR No.:

Stage 1: Setting Out

  • Verify layout has been checked and marked appropriately.
  • Confirm clearance from other MEP and civil services.
  • Ensure excavation has been completed as per approved drawings.
  • Confirm suitability of backfilling and compaction before installation.

Stage 2: Installation Checks

  1. Ensure all pipe routings and sizes conform to approved shop drawings.
  2. Verify that all materials used are as per the approved material submittals.
  3. Check the bedding surface to ensure it is free from hard protrusions or large stones and is properly prepared.
  4. Confirm that the installed pipe levels and slopes match the approved drawings.
  5. Verify that pressure testing of pipes has been completed (1.5 times working pressure for 24 hours).
  6. Ensure that all open pipe ends are sealed to prevent ingress of construction debris.
  7. Confirm that pipe expansion provisions are made at building expansion joints and other required locations.
  8. Check that approved detectable warning tapes are installed at the required level above the piping.

Approvals and Sign-Off

  • Subcontractor QA/QC
    • Name:
    • Signature:
    • Date:
  • Contractor QA/QC
    • Name:
    • Signature:
    • Date:
  • Consultant Representative
    • Name:
    • Signature:
    • Date:

Hydrostatic Test Report

Ref. No:
Revision No: 0
Page: 1 of 1


Project Details

Subcontractor:
Contractor:
Section of Work: Water Supply
Location:
Level:
Work Inspection Request (WIR) No.:


Test Information

Area / Location:
System: Water Supply
Drawing No.:
Drawing Revision:


Type of Test

  • Test Method: Hydrostatic Test ✔
  • Test Medium: Water ✔

Piping System

  • Hot and Cold Water Supply Pipe Work

Test Parameters

  • Working Pressure:
  • Test Pressure: 1.5 × Working Pressure
  • Minimum Ambient Temperature:
  • Test Medium Temperature:
  • Date of Test:
  • Duration of Test: Minimum 2 Hours
  • Testing Fluid/Gas: Water
  • Start Time:
  • Finish Time:
  • Initial Pressure:
  • Final Pressure:
  • Pressure Gauge Number:
  • Calibration Due Date:

Remarks

(Insert observations, notes, or specific remarks about the test here)





Test Results

☐ No leaks were observed during the test duration. Test results are acceptable.
☐ Test results are not acceptable. Rectify leaks and retest.


Sign-Off and Approval

Subcontractor QA/QC:

  • Name:
  • Signature:
  • Date:

Contractor QA/QC:

  • Name:
  • Signature:
  • Date:

Consultant Representative:

  • Name:
  • Signature:
  • Date:
smoke-8558784_1280

Method Statement for Testing of Fire Alarm System:

Contents

  1. Introduction
  2. Test Instruments/Tools Required
  3. Reference Standards
  4. Test Procedures
  5. Test Execution
  6. Fire Dampers
  7. Test Record Sheets

1. Introduction

1.1 This fire alarm testing method statement outlines the step-by-step process for inspecting and testing the fire alarm system at this project site.

1.2 The contractor may further enhance or expand upon these guidelines, subject to agreement with the Project M&E Engineer and Independent Testing and Commissioning Engineer.

1.3 The primary goal of this procedure is to verify that the fire alarm system’s installation and performance align with the M&E design intent.

1.4 The contractor must become familiar with the existing system’s operation, including the cause and effect scenarios. Upon completing the commissioning, the contractor will perform comprehensive cause and effect testing on the new fire alarm installation to ensure compatibility and consistency with the existing configuration.


2. Test Instruments / Tools Required

2.1 All testing instruments must have a valid calibration certificate (at least 6 months remaining) traceable to international standards.

2.2 Instruments should be suitable for the expected test parameters and provide accurate readings, ideally at their mid-range scale.

2.3 The following tools and equipment are required for fire alarm system testing:

  • Calibrated Multimeter
  • Aerosol Smoke Canisters
  • Heat Source
  • Walkie Talkies

3. Reference Standards

3.1 The testing procedure adheres to the following British Standards:

  • BS 6266:2002 – Code of Practice for Fire Protection for Electronic Equipment Installations
  • BS 5839:2002 – Code of Practice for Fire Detection and Alarm Systems for Buildings

All testing and commissioning activities must comply with these standards.


4. Test Procedures

Before testing begins, ensure the following:

4.1 Verify correct placement and installation of device housings and components.
4.2 Confirm that appropriate cable types are used.
4.3 Ensure all high and low voltage cables have passed electrical testing, and power (AC/DC) is available at correct voltages.

Note: Never connect devices until wiring tests are approved to avoid potential damage.

4.4 Confirm proper labeling of all system components per design specifications.
4.5 Verify device numbering and alarm message descriptions match the latest architectural layout or room names.
4.6 Perform insulation resistance tests, polarity checks, and loop resistance measurements.
4.7 Measure addressable circuit capacitance and inductance where applicable.
4.8 Confirm all equipment (detectors, sounders, etc.) is properly installed per manufacturer instructions.
4.9 Check suppressors and polarizing diodes on electro-mechanical sounders.
4.10 Ensure short circuit isolators are installed at specified intervals.
4.11 Confirm battery sizing by recording voltage and current data. Simulate standby operation and record performance.


5. Test Execution

Before starting, print the list of all addressable devices and confirm:

  • Devices are installed and in normal status
  • No devices are isolated or malfunctioning

5.1 Functional Testing:

5.1.1 Test call points with a key or by breaking glass.
5.1.2 Use aerosol smoke to test smoke detectors.
5.1.3 Apply heat (e.g., hair dryer) to test heat detectors without damaging components.
5.1.4 Confirm proper operation of all input/output devices.

5.2 At Each Detector:

5.2.1 Ensure LED lights up during detection.

5.3 At the Fire Alarm Control Panel:

5.3.1 RED fire lamp should light.
5.3.2 Internal sounder must activate.
5.3.3 Relevant fire zone must be indicated.
5.3.4 Correct text message should display and print.
5.3.5 Appropriate sounders should activate.
5.3.6 Switching relays should change state.

5.4 After Alarm is Muted:

5.4.1 Internal sounder remains audible.
5.4.2 Fire zone still indicated.
5.4.3 ‘Fire’ lamp stays illuminated.

5.5 Fault Testing:

5.5.1 Remove each detector; verify ‘Fault’ lamp and sounder activate.
5.5.2 Ensure fault message displays and prints.
5.5.3 Replace components and reset the system to confirm restoration.

5.6 Sounder Walk Test:

5.6.1 Program panel for walk test.
5.6.2 Walk the site and confirm sounder operation.
5.6.3 Reset panel to normal after test.

Alternatively, activate alarm in ‘Test’ mode and verify sounders.

5.7 Audibility Test:

5.7.1 Activate alarms; use calibrated sound level meter.
5.7.2 Acceptable sound level is minimum 65dB(A) or 5dB(A) above ambient noise sustained for over 30 seconds.
5.7.3 Repeat test during full occupancy if initially unoccupied.
5.7.4 Use BS5969 Type 2 compliant meter, slow response, A-weighted.

5.8 Short Circuit Testing:

Introduce shorts at intervals to verify isolators and ensure fire system functionality is retained, except at the faulted segment.

5.9 Battery Testing:

  • Measure standby and alarm currents using multimeter across fuse terminals.
  • Isolate mains, record performance in both standby and alarm modes.
  • Simulate a full mains failure and verify backup battery operation during full alarm for required duration.

6. Fire Dampers

6.1 The responsible trade contractor shall submit a comprehensive fire damper schedule including reference numbers, locations, type, and size (base build and fit-out).

6.2 The schedule must confirm that drop tests were completed and that dampers are accessible and resettable. Upon confirmation, 100% of dampers will be witnessed by the Independent Testing and Commissioning Engineer, and subsequently reviewed by the Fire Marshal.


7. Test Record Sheets

The following documentation must be completed and submitted:

  • Cable Test Sheets
  • Marked-Up Floor Layout Drawings
  • Complete Device List with Alarm Messages
  • Fire Alarm Panel Test Result Printouts

What is Building Services Planning Manual

Engineering Drawing Submittal & Approval

 Drawing Submittal & Approval

Method Statement (MS) Submittal & Approval

Mechanical System (HVAC)

Electrical System

Plumbing and Fire Fighting System

Construction

Project Milestone Requirements

Mechanical System

Electrical System

Plumbing System

Fire Fighting System