π 1. Purpose
This method statement outlines the procedures for Testing & Commissioning of Ventilation and Exhaust Fans in accordance with project specifications and approved shop drawings.
π 2. Scope
Covers the complete process of Testing & Commissioning of all Ventilation and General Exhaust Fan Units per:
- Project Requirements
- Manufacturer Instructions
- Approved Shop Drawings
π 3. References
- β Latest approved HVAC fans shop drawings
- β Project Quality Plan (PQP)
- β Project HSE Plan
- β Material Approvals
π 4. Definitions
Here are key abbreviations used:
- PQP β Project Quality Plan
- PSP β Project Safety Plan
- QCP β Quality Control Procedure
- WIR β Work Inspection Request
- MIR β Material Inspection Request
- ASHRAE β Air Conditioning Society
- SMACNA, ARI, ASME, NFPA, UL, BMS, NEMA, AMCA, TEFC, BS β Industry codes and standards
π 5. Responsibilities
π¨βπΌ Project Manager
- Ensure smooth execution per project plan
- Oversee safety & quality compliance
π·ββοΈ Construction Manager
- Control and supervise site activities
- Coordinate with QA/QC and Site Engineers
π§βπ» Site Engineer
- Implement method statements
- Monitor progress and ensure coordination
- Respond to consultant comments
π§βπ§ QA/QC Engineer
- Monitor site execution as per specs
- Raise WIRs/MIRs and ensure inspections
- Assist during consultant inspections
π¨βπ§ Site Foreman
- Execute tasks in coordination with Site Engineer
- Daily work reporting
- Ensure safety and quality compliance
π· Safety Officer
- Enforce HSE Plan
- Ensure proper PPE and tools are used
- Monitor site for potential hazards
π¦ Store Keeper
- Manage proper material storage
- Acknowledge deliveries in coordination with QA/QC
π 6. Equipments Required
- π§ Basic Electrical Tools
- π¬οΈ Pitot Tube / Air Flow Meters
- π¨ Anemometer
- π Multimeter (FLA reading)
- π Tachometer (Fan RPM)
- βοΈ Marker
- π§° Toolbox
- πͺ Step Ladder
π 7. Procedure
β General HSE Requirements
- Safety signs and PPE mandatory
- Commissioning Kick-Off Meeting
β Pre-Commissioning Checklist
- PTW system in place
- Pre-safety inspection
- Approval of latest installation drawings
- Inspected and approved materials/equipment
- LOTO system active
- Inspection tools ready
- Stable power supply
βοΈ Commissioning Steps
π Functional Test
- Ensure pre-commissioning completed
- Obtain approved PTW
- Verify control panel commissioning
- Check line voltage
- Test motor operation and direction
- Observe for unusual noises or vibrations
- Record motor current and voltage readings
- Ensure BMS control devices function properly
π Testing & Balancing
- Conducted by third-party agency
- Follow approved procedures and specs
π Post-Test Reinstatement
- Sign-off on check/test sheets
- Remove test instruments
- Confirm no faults in system
- Lock the control panel
π οΈ Preservation and Flat Condition
- Ensure stable, complete power supply
- Restrict access to authorized personnel only
- Confirm no overheating or loose connections
π 8. System-Specific Commissioning
π§ͺ Chemical Rooms
- Operated via control panel or emergency push button
- Fan starts during chemical spills
π³ Kitchen Fans
- OFF: Both extract & make-up fans off
- ON: Both fans operate from kitchen control panel
π¬οΈ General Fans
- OFF: Supply and extract fans off
- ON: Controlled via local switch at normal operation
π§― Staircase & Lift Pressurization Fans
- Controlled by Fire Alarm Control Panel (FACP)
- BMS monitors fan run/trip status and alarms
π Generator Room
- Fan interlocked with generator panel
- Fan starts when generator operates
π½ Toilet Exhaust Fans
- Operated via roof control panel
- Motorized damper opens with fan
- Failure triggers automatic fan and damper operation
π 9. Attachments
- π Inspection & Test Plan
- π Pre-Commissioning Check Sheet
- β Testing & Commissioning Check Sheet
- π·οΈ Commissioning Certificate Form
- π Handover Certificate Form
- β Punch List Form
- β οΈ Risk Assessment
- π Fans Schedule
- πΊοΈ Drawing Attachments